161 |
NOMOR |
URAIAN KEGIATAN |
KOEF. |
SAT |
HARGA SATUAN |
HARGA |
24.1.2.25 |
Pengurugan Abu Batu |
|
500 Biji |
|
|
|
Upah: |
|
|
|
|
|
|
|
|
Jumlah |
0,00 |
|
Bahan/Material: |
|
|
|
|
|
|
|
|
Jumlah |
0,00 |
|
Sewa Peralatan: |
|
|
|
|
|
|
|
|
Jumlah |
0,00 |
|
|
|
|
Nilai HSPK |
0,00 |
| 2019 | 24.1.2.25 | Pengurugan Abu Batu | 500 Biji | 0,00 | Tidak Dipakai | |
162 |
NOMOR |
URAIAN KEGIATAN |
KOEF. |
SAT |
HARGA SATUAN |
HARGA |
24.1.2.36 |
Pengurugan 1 m3 Sirtu Padat |
|
M3 |
|
|
|
Upah: |
|
|
|
|
23.2.4.1.1.1 |
Mandor |
0.025 |
Orang Hari |
28.000,00 |
700,00 |
23.2.4.1.5.1 |
Tenaga Kasar |
0.25 |
Orang Hari |
110.000,00 |
27.500,00 |
|
|
|
|
Jumlah |
28.200,00 |
|
Bahan/Material: |
|
|
|
|
20.1.1.4.5.1 |
Sirtu |
1.2 |
M3 |
307.682,00 |
369.218,41 |
|
|
|
|
Jumlah |
369.218,41 |
|
Sewa Peralatan: |
|
|
|
|
23.2.5.11.6.12 |
Sewa Stemper |
0.0088 |
jam |
109.400,00 |
962,72 |
|
|
|
|
Jumlah |
962,72 |
|
|
|
|
Nilai HSPK |
398.381,13 |
| 2019 | 24.1.2.36 | Pengurugan 1 m3 Sirtu Padat | M3 | 398.381,13 | Tidak Dipakai | |
163 |
NOMOR |
URAIAN KEGIATAN |
KOEF. |
SAT |
HARGA SATUAN |
HARGA |
24.1.2.35 |
Pengurugan 1 m3 Dengan Tanah Urug |
|
M3 |
|
|
|
Upah: |
|
|
|
|
23.2.4.1.1.1 |
Mandor |
0.01 |
Orang Hari |
28.000,00 |
280,00 |
23.2.4.1.5.1 |
Tenaga Kasar |
0.3 |
Orang Hari |
110.000,00 |
33.000,00 |
|
|
|
|
Jumlah |
33.280,00 |
|
Bahan/Material: |
|
|
|
|
20.1.1.4.1.4 |
Pasir Timbun/urug |
1.2 |
M3 |
141.426,00 |
169.711,21 |
|
|
|
|
Jumlah |
169.711,21 |
|
Sewa Peralatan: |
|
|
|
|
|
|
|
|
Jumlah |
0,00 |
|
|
|
|
Nilai HSPK |
202.991,21 |
| 2019 | 24.1.2.35 | Pengurugan 1 m3 Dengan Tanah Urug | M3 | 202.991,21 | Tidak Dipakai | |
164 |
NOMOR |
URAIAN KEGIATAN |
KOEF. |
SAT |
HARGA SATUAN |
HARGA |
24.1.1.4 |
Pengukuran dan Pembuatan Bouwplank |
|
M1 |
|
|
|
Upah: |
|
|
|
|
123.1.1.1.1.5 |
Kepala Tukang |
0.01 |
OH |
236.200,00 |
2.362,00 |
123.1.1.1.1.6 |
Mandor |
0.005 |
OH |
206.800,00 |
1.034,00 |
123.1.1.1.1.14 |
Pekerja Terlatih |
0.1 |
OH |
150.800,00 |
15.080,00 |
123.1.1.1.1.23 |
Tukang |
0.1 |
OH |
177.500,00 |
17.750,00 |
|
|
|
|
Jumlah |
36.226,00 |
|
Bahan/Material: |
|
|
|
|
117.1.1.1.22.87 |
Papan/ Kaso Kayu Kelas III |
0.012 |
M3 |
6.403.200,00 |
76.838,40 |
117.1.1.1.22.233 |
Paku 2-5 inchi |
0.02 |
Kg |
34.700,00 |
694,00 |
|
|
|
|
Jumlah |
77.532,40 |
|
Sewa Peralatan: |
|
|
|
|
|
|
|
|
Jumlah |
0,00 |
|
|
|
|
Nilai HSPK |
113.758,40 |
| 2020 | 24.1.1.4 | Pengukuran dan Pembuatan Bouwplank | M1 | 113.758,40 | Tidak Dipakai | |
165 |
NOMOR |
URAIAN KEGIATAN |
KOEF. |
SAT |
HARGA SATUAN |
HARGA |
24.8.2.24 |
Penghamparan Lapis Perm. Aspal Beton Laston (AC) tb. 4 cm |
|
10 Pcs |
|
|
|
Upah: |
|
|
|
|
|
|
|
|
Jumlah |
0,00 |
|
Bahan/Material: |
|
|
|
|
|
|
|
|
Jumlah |
0,00 |
|
Sewa Peralatan: |
|
|
|
|
|
|
|
|
Jumlah |
0,00 |
|
|
|
|
Nilai HSPK |
0,00 |
| 2018 | 24.8.2.24 | Penghamparan Lapis Perm. Aspal Beton Laston (AC) tb. 4 cm | 10 Pcs | 0,00 | Tidak Dipakai | |
166 |
NOMOR |
URAIAN KEGIATAN |
KOEF. |
SAT |
HARGA SATUAN |
HARGA |
24.8.2.24 |
Penghamparan Lapis Perm. Aspal Beton Laston (AC) tb. 4 cm |
|
10 Pcs |
|
|
|
Upah: |
|
|
|
|
|
|
|
|
Jumlah |
0,00 |
|
Bahan/Material: |
|
|
|
|
|
|
|
|
Jumlah |
0,00 |
|
Sewa Peralatan: |
|
|
|
|
|
|
|
|
Jumlah |
0,00 |
|
|
|
|
Nilai HSPK |
0,00 |
| 2019 | 24.8.2.24 | Penghamparan Lapis Perm. Aspal Beton Laston (AC) tb. 4 cm | 10 Pcs | 0,00 | Tidak Dipakai | |
167 |
NOMOR |
URAIAN KEGIATAN |
KOEF. |
SAT |
HARGA SATUAN |
HARGA |
24.8.2.22 |
Penghamparan ATB tb. 6 cm |
|
potong |
|
|
|
Upah: |
|
|
|
|
|
|
|
|
Jumlah |
0,00 |
|
Bahan/Material: |
|
|
|
|
|
|
|
|
Jumlah |
0,00 |
|
Sewa Peralatan: |
|
|
|
|
|
|
|
|
Jumlah |
0,00 |
|
|
|
|
Nilai HSPK |
0,00 |
| 2018 | 24.8.2.22 | Penghamparan ATB tb. 6 cm | potong | 0,00 | Tidak Dipakai | |
168 |
NOMOR |
URAIAN KEGIATAN |
KOEF. |
SAT |
HARGA SATUAN |
HARGA |
24.8.2.22 |
Penghamparan ATB tb. 6 cm |
|
potong |
|
|
|
Upah: |
|
|
|
|
|
|
|
|
Jumlah |
0,00 |
|
Bahan/Material: |
|
|
|
|
|
|
|
|
Jumlah |
0,00 |
|
Sewa Peralatan: |
|
|
|
|
|
|
|
|
Jumlah |
0,00 |
|
|
|
|
Nilai HSPK |
0,00 |
| 2019 | 24.8.2.22 | Penghamparan ATB tb. 6 cm | potong | 0,00 | Tidak Dipakai | |
169 |
NOMOR |
URAIAN KEGIATAN |
KOEF. |
SAT |
HARGA SATUAN |
HARGA |
24.8.2.23 |
Penghamparan ATB tb. 4 cm |
|
potong |
|
|
|
Upah: |
|
|
|
|
|
|
|
|
Jumlah |
0,00 |
|
Bahan/Material: |
|
|
|
|
|
|
|
|
Jumlah |
0,00 |
|
Sewa Peralatan: |
|
|
|
|
|
|
|
|
Jumlah |
0,00 |
|
|
|
|
Nilai HSPK |
0,00 |
| 2018 | 24.8.2.23 | Penghamparan ATB tb. 4 cm | potong | 0,00 | Tidak Dipakai | |
170 |
NOMOR |
URAIAN KEGIATAN |
KOEF. |
SAT |
HARGA SATUAN |
HARGA |
24.8.2.23 |
Penghamparan ATB tb. 4 cm |
|
potong |
|
|
|
Upah: |
|
|
|
|
|
|
|
|
Jumlah |
0,00 |
|
Bahan/Material: |
|
|
|
|
|
|
|
|
Jumlah |
0,00 |
|
Sewa Peralatan: |
|
|
|
|
|
|
|
|
Jumlah |
0,00 |
|
|
|
|
Nilai HSPK |
0,00 |
| 2019 | 24.8.2.23 | Penghamparan ATB tb. 4 cm | potong | 0,00 | Tidak Dipakai | |
171 |
NOMOR |
URAIAN KEGIATAN |
KOEF. |
SAT |
HARGA SATUAN |
HARGA |
24.1.2.10 |
Penggalian Tanah Lumpur |
|
500 Biji |
|
|
|
Upah: |
|
|
|
|
|
|
|
|
Jumlah |
0,00 |
|
Bahan/Material: |
|
|
|
|
|
|
|
|
Jumlah |
0,00 |
|
Sewa Peralatan: |
|
|
|
|
|
|
|
|
Jumlah |
0,00 |
|
|
|
|
Nilai HSPK |
0,00 |
| 2018 | 24.1.2.10 | Penggalian Tanah Lumpur | 500 Biji | 0,00 | Tidak Dipakai | |
172 |
NOMOR |
URAIAN KEGIATAN |
KOEF. |
SAT |
HARGA SATUAN |
HARGA |
24.1.2.10 |
Penggalian Tanah Lumpur |
|
M3 |
|
|
|
Upah: |
|
|
|
|
23.2.4.1.1.1 |
Mandor |
0.045 |
Orang Hari |
28.000,00 |
1.260,00 |
23.2.4.1.5.1 |
Tenaga Kasar |
1.2 |
Orang Hari |
110.000,00 |
132.000,01 |
|
|
|
|
Jumlah |
133.260,01 |
|
Bahan/Material: |
|
|
|
|
|
|
|
|
Jumlah |
0,00 |
|
Sewa Peralatan: |
|
|
|
|
|
|
|
|
Jumlah |
0,00 |
|
|
|
|
Nilai HSPK |
133.260,01 |
| 2019 | 24.1.2.10 | Penggalian Tanah Lumpur | M3 | 133.260,01 | Tidak Dipakai | |
173 |
NOMOR |
URAIAN KEGIATAN |
KOEF. |
SAT |
HARGA SATUAN |
HARGA |
24.1.2.5 |
Penggalian Tanah Lumpur |
|
M3 |
|
|
|
Upah: |
|
|
|
|
123.1.1.1.1.5 |
Kepala Tukang |
0 |
OH |
236.200,00 |
0,00 |
123.1.1.1.1.6 |
Mandor |
0.045 |
OH |
206.800,00 |
9.306,00 |
123.1.1.1.1.14 |
Pekerja Terlatih |
1.2 |
OH |
150.800,00 |
180.960,01 |
123.1.1.1.1.23 |
Tukang |
0 |
OH |
177.500,00 |
0,00 |
|
|
|
|
Jumlah |
190.266,01 |
|
Bahan/Material: |
|
|
|
|
|
|
|
|
Jumlah |
0,00 |
|
Sewa Peralatan: |
|
|
|
|
|
|
|
|
Jumlah |
0,00 |
|
|
|
|
Nilai HSPK |
190.266,01 |
| 2020 | 24.1.2.5 | Penggalian Tanah Lumpur | M3 | 190.266,01 | Tidak Dipakai | |
174 |
NOMOR |
URAIAN KEGIATAN |
KOEF. |
SAT |
HARGA SATUAN |
HARGA |
24.1.2.3 |
Penggalian Tanah Keras sedalam s.d. 1 m |
|
M3 |
|
|
|
Upah: |
|
|
|
|
123.1.1.1.1.5 |
Kepala Tukang |
0 |
OH |
236.200,00 |
0,00 |
123.1.1.1.1.6 |
Mandor |
0.032 |
OH |
206.800,00 |
6.617,60 |
123.1.1.1.1.14 |
Pekerja Terlatih |
1 |
OH |
150.800,00 |
150.800,00 |
123.1.1.1.1.23 |
Tukang |
0 |
OH |
177.500,00 |
0,00 |
|
|
|
|
Jumlah |
157.417,60 |
|
Bahan/Material: |
|
|
|
|
|
|
|
|
Jumlah |
0,00 |
|
Sewa Peralatan: |
|
|
|
|
|
|
|
|
Jumlah |
0,00 |
|
|
|
|
Nilai HSPK |
157.417,60 |
| 2020 | 24.1.2.3 | Penggalian Tanah Keras sedalam s.d. 1 m | M3 | 157.417,60 | Tidak Dipakai | |
175 |
NOMOR |
URAIAN KEGIATAN |
KOEF. |
SAT |
HARGA SATUAN |
HARGA |
24.1.2.30 |
Penggalian Tanah Keras Sedalam 1 m |
|
M3 |
|
|
|
Upah: |
|
|
|
|
23.2.4.1.1.1 |
Mandor |
0.032 |
Orang Hari |
28.000,00 |
896,00 |
23.2.4.1.5.1 |
Tenaga Kasar |
1 |
Orang Hari |
110.000,00 |
110.000,00 |
|
|
|
|
Jumlah |
110.896,00 |
|
Bahan/Material: |
|
|
|
|
|
|
|
|
Jumlah |
0,00 |
|
Sewa Peralatan: |
|
|
|
|
|
|
|
|
Jumlah |
0,00 |
|
|
|
|
Nilai HSPK |
110.896,00 |
| 2019 | 24.1.2.30 | Penggalian Tanah Keras Sedalam 1 m | M3 | 110.896,00 | Tidak Dipakai | |
176 |
NOMOR |
URAIAN KEGIATAN |
KOEF. |
SAT |
HARGA SATUAN |
HARGA |
24.1.2.8 |
Penggalian Tanah Keras |
|
500 Biji |
|
|
|
Upah: |
|
|
|
|
|
|
|
|
Jumlah |
0,00 |
|
Bahan/Material: |
|
|
|
|
|
|
|
|
Jumlah |
0,00 |
|
Sewa Peralatan: |
|
|
|
|
|
|
|
|
Jumlah |
0,00 |
|
|
|
|
Nilai HSPK |
0,00 |
| 2018 | 24.1.2.8 | Penggalian Tanah Keras | 500 Biji | 0,00 | Tidak Dipakai | |
177 |
NOMOR |
URAIAN KEGIATAN |
KOEF. |
SAT |
HARGA SATUAN |
HARGA |
24.1.2.8 |
Penggalian Tanah Keras |
|
500 Biji |
|
|
|
Upah: |
|
|
|
|
|
|
|
|
Jumlah |
0,00 |
|
Bahan/Material: |
|
|
|
|
|
|
|
|
Jumlah |
0,00 |
|
Sewa Peralatan: |
|
|
|
|
|
|
|
|
Jumlah |
0,00 |
|
|
|
|
Nilai HSPK |
0,00 |
| 2019 | 24.1.2.8 | Penggalian Tanah Keras | 500 Biji | 0,00 | Tidak Dipakai | |
178 |
NOMOR |
URAIAN KEGIATAN |
KOEF. |
SAT |
HARGA SATUAN |
HARGA |
24.1.2.12 |
Penggalian Tanah dengan Alat Berat |
|
500 Biji |
|
|
|
Upah: |
|
|
|
|
|
|
|
|
Jumlah |
0,00 |
|
Bahan/Material: |
|
|
|
|
|
|
|
|
Jumlah |
0,00 |
|
Sewa Peralatan: |
|
|
|
|
|
|
|
|
Jumlah |
0,00 |
|
|
|
|
Nilai HSPK |
0,00 |
| 2018 | 24.1.2.12 | Penggalian Tanah dengan Alat Berat | 500 Biji | 0,00 | Tidak Dipakai | |
179 |
NOMOR |
URAIAN KEGIATAN |
KOEF. |
SAT |
HARGA SATUAN |
HARGA |
24.1.2.12 |
Penggalian Tanah dengan Alat Berat |
|
M3 |
|
|
|
Upah: |
|
|
|
|
23.2.4.1.1.1 |
Mandor |
0.007 |
Orang Hari |
28.000,00 |
196,00 |
23.2.4.1.5.1 |
Tenaga Kasar |
0.226 |
Orang Hari |
110.000,00 |
24.860,00 |
|
|
|
|
Jumlah |
25.056,00 |
|
Bahan/Material: |
|
|
|
|
|
|
|
|
Jumlah |
0,00 |
|
Sewa Peralatan: |
|
|
|
|
23.2.5.9.4.3 |
Sewa Dump Truk |
0.067 |
jam |
69.200,00 |
4.636,40 |
23.2.5.11.1.1 |
Sewa Escavator |
0.067 |
jam |
138.400,00 |
9.272,80 |
|
|
|
|
Jumlah |
13.909,20 |
|
|
|
|
Nilai HSPK |
38.965,20 |
| 2019 | 24.1.2.12 | Penggalian Tanah dengan Alat Berat | M3 | 38.965,20 | Tidak Dipakai | |
180 |
NOMOR |
URAIAN KEGIATAN |
KOEF. |
SAT |
HARGA SATUAN |
HARGA |
24.1.2.7 |
Penggalian Tanah dengan Alat Berat |
|
M3 |
|
|
|
Upah: |
|
|
|
|
123.1.1.1.1.5 |
Kepala Tukang |
0 |
OH |
236.200,00 |
0,00 |
123.1.1.1.1.6 |
Mandor |
0.007 |
OH |
206.800,00 |
1.447,60 |
123.1.1.1.1.14 |
Pekerja Terlatih |
0.226 |
OH |
150.800,00 |
34.080,80 |
123.1.1.1.1.23 |
Tukang |
0 |
OH |
177.500,00 |
0,00 |
|
|
|
|
Jumlah |
35.528,40 |
|
Bahan/Material: |
|
|
|
|
|
|
|
|
Jumlah |
0,00 |
|
Sewa Peralatan: |
|
|
|
|
123.2.2.1.2.24 |
Dump Truck |
0.067 |
jam |
513.600,00 |
34.411,20 |
123.2.2.1.2.28 |
Excavator 6 M3 |
0.067 |
jam |
584.300,00 |
39.148,10 |
|
|
|
|
Jumlah |
73.559,30 |
|
|
|
|
Nilai HSPK |
109.087,70 |
| 2020 | 24.1.2.7 | Penggalian Tanah dengan Alat Berat | M3 | 109.087,70 | Tidak Dipakai | |