181 |
NOMOR |
URAIAN KEGIATAN |
KOEF. |
SAT |
HARGA SATUAN |
HARGA |
24.1.5.4 |
Pekerjaan atap pelana rangkap atap Besi Baja Ringan Canal C 75 bahan atap seng/spandek/zincalum |
|
M2 |
|
|
|
Upah: |
|
|
|
|
123.1.1.1.1.5 |
Kepala Tukang |
0.06 |
OH |
236.200,00 |
14.172,00 |
123.1.1.1.1.6 |
Mandor |
0.02 |
OH |
206.800,00 |
4.136,00 |
123.1.1.1.1.14 |
Pekerja Terlatih |
0.6 |
OH |
150.800,00 |
90.480,00 |
123.1.1.1.1.25 |
Tukang Besi |
0.6 |
OH |
177.500,00 |
106.500,00 |
|
|
|
|
Jumlah |
215.288,01 |
|
Bahan/Material: |
|
|
|
|
117.1.1.1.8.5 |
Baja Ringan Canal C75 |
3.065 |
batang |
81.200,00 |
248.878,00 |
|
|
|
|
Jumlah |
248.878,00 |
|
Sewa Peralatan: |
|
|
|
|
|
|
|
|
Jumlah |
0,00 |
|
|
|
|
Nilai HSPK |
464.166,01 |
| 2020 | 24.1.5.4 | Pekerjaan atap pelana rangkap atap Besi Baja Ringan Canal C 75 bahan atap seng/spandek/zincalum | M2 | 464.166,01 | Tidak Dipakai | |
182 |
NOMOR |
URAIAN KEGIATAN |
KOEF. |
SAT |
HARGA SATUAN |
HARGA |
24.1.2.4 |
Penggalian Tanah Cadas/Rabat sedalam s.d. 1 m |
|
M3 |
|
|
|
Upah: |
|
|
|
|
123.1.1.1.1.5 |
Kepala Tukang |
0 |
OH |
236.200,00 |
0,00 |
123.1.1.1.1.6 |
Mandor |
0.06 |
OH |
206.800,00 |
12.408,00 |
123.1.1.1.1.14 |
Pekerja Terlatih |
1.5 |
OH |
150.800,00 |
226.200,00 |
123.1.1.1.1.23 |
Tukang |
0 |
OH |
177.500,00 |
0,00 |
|
|
|
|
Jumlah |
238.608,00 |
|
Bahan/Material: |
|
|
|
|
|
|
|
|
Jumlah |
0,00 |
|
Sewa Peralatan: |
|
|
|
|
|
|
|
|
Jumlah |
0,00 |
|
|
|
|
Nilai HSPK |
238.608,00 |
| 2020 | 24.1.2.4 | Penggalian Tanah Cadas/Rabat sedalam s.d. 1 m | M3 | 238.608,00 | Tidak Dipakai | |
183 |
NOMOR |
URAIAN KEGIATAN |
KOEF. |
SAT |
HARGA SATUAN |
HARGA |
24.1.12.4 |
Pemasangan Dasar Saluran R.10 (1/2 lingkaran) |
|
meter |
|
|
|
Upah: |
|
|
|
|
123.1.1.1.1.5 |
Kepala Tukang |
0 |
OH |
236.200,00 |
0,00 |
123.1.1.1.1.6 |
Mandor |
0.0238 |
OH |
206.800,00 |
4.921,84 |
123.1.1.1.1.14 |
Pekerja Terlatih |
0.475 |
OH |
150.800,00 |
71.630,00 |
123.1.1.1.1.23 |
Tukang |
0 |
OH |
177.500,00 |
0,00 |
|
|
|
|
Jumlah |
76.551,84 |
|
Bahan/Material: |
|
|
|
|
117.1.1.1.22.454 |
Got Talang R. 10 (1/2 Lingkaran) |
1 |
buah |
39.100,00 |
39.100,00 |
|
|
|
|
Jumlah |
39.100,00 |
|
Sewa Peralatan: |
|
|
|
|
|
|
|
|
Jumlah |
0,00 |
|
|
|
|
Nilai HSPK |
115.651,84 |
| 2020 | 24.1.12.4 | Pemasangan Dasar Saluran R.10 (1/2 lingkaran) | meter | 115.651,84 | Tidak Dipakai | |
184 |
NOMOR |
URAIAN KEGIATAN |
KOEF. |
SAT |
HARGA SATUAN |
HARGA |
24.7.2.4 |
Pemasangan Saklar Ganda |
|
cup |
|
|
|
Upah: |
|
|
|
|
|
|
|
|
Jumlah |
0,00 |
|
Bahan/Material: |
|
|
|
|
|
|
|
|
Jumlah |
0,00 |
|
Sewa Peralatan: |
|
|
|
|
|
|
|
|
Jumlah |
0,00 |
|
|
|
|
Nilai HSPK |
0,00 |
| 2018 | 24.7.2.4 | Pemasangan Saklar Ganda | cup | 0,00 | Tidak Dipakai | |
185 |
NOMOR |
URAIAN KEGIATAN |
KOEF. |
SAT |
HARGA SATUAN |
HARGA |
24.1.8.4 |
Pemasangan Lantai Keramik ukuran 60x60 cm |
|
M2 |
|
|
|
Upah: |
|
|
|
|
123.1.1.1.1.5 |
Kepala Tukang |
0.035 |
OH |
236.200,00 |
8.267,00 |
123.1.1.1.1.6 |
Mandor |
0.035 |
OH |
206.800,00 |
7.238,00 |
123.1.1.1.1.14 |
Pekerja Terlatih |
0.7 |
OH |
150.800,00 |
105.560,00 |
123.1.1.1.1.23 |
Tukang |
0.35 |
OH |
177.500,00 |
62.125,00 |
|
|
|
|
Jumlah |
183.190,00 |
|
Bahan/Material: |
|
|
|
|
117.1.1.1.2.54 |
Semen PC / Kg |
10.4 |
Kg |
2.600,00 |
27.040,00 |
117.1.1.1.2.58 |
Semen Warna |
1.62 |
Zak |
114.800,00 |
185.976,00 |
117.1.1.1.4.4 |
Pasir Pasang |
0.045 |
M3 |
180.100,00 |
8.104,50 |
117.1.1.12.1.77 |
Keramik 60 x 60 cm |
3 |
kotak |
151.900,00 |
455.700,00 |
|
|
|
|
Jumlah |
676.820,50 |
|
Sewa Peralatan: |
|
|
|
|
|
|
|
|
Jumlah |
0,00 |
|
|
|
|
Nilai HSPK |
860.010,50 |
| 2020 | 24.1.8.4 | Pemasangan Lantai Keramik ukuran 60x60 cm | M2 | 860.010,50 | Tidak Dipakai | |
186 |
NOMOR |
URAIAN KEGIATAN |
KOEF. |
SAT |
HARGA SATUAN |
HARGA |
24.3.1.4 |
Lantai Kerja K-100 |
|
500 Biji |
|
|
|
Upah: |
|
|
|
|
|
|
|
|
Jumlah |
0,00 |
|
Bahan/Material: |
|
|
|
|
|
|
|
|
Jumlah |
0,00 |
|
Sewa Peralatan: |
|
|
|
|
|
|
|
|
Jumlah |
0,00 |
|
|
|
|
Nilai HSPK |
0,00 |
| 2018 | 24.3.1.4 | Lantai Kerja K-100 | 500 Biji | 0,00 | Tidak Dipakai | |
187 |
NOMOR |
URAIAN KEGIATAN |
KOEF. |
SAT |
HARGA SATUAN |
HARGA |
24.2.1.4 |
Pemasangan Trucuk Bambu φ 10 s/d 12 - P.3 m |
|
batang |
|
|
|
Upah: |
|
|
|
|
|
|
|
|
Jumlah |
0,00 |
|
Bahan/Material: |
|
|
|
|
|
|
|
|
Jumlah |
0,00 |
|
Sewa Peralatan: |
|
|
|
|
|
|
|
|
Jumlah |
0,00 |
|
|
|
|
Nilai HSPK |
0,00 |
| 2018 | 24.2.1.4 | Pemasangan Trucuk Bambu φ 10 s/d 12 - P.3 m | batang | 0,00 | Tidak Dipakai | |
188 |
NOMOR |
URAIAN KEGIATAN |
KOEF. |
SAT |
HARGA SATUAN |
HARGA |
24.1.14.4 |
Pekerjaan Besi Pipa Galvanis 1 1/4 " (Medium) |
|
meter |
|
|
|
Upah: |
|
|
|
|
123.1.1.1.1.5 |
Kepala Tukang |
0.04 |
OH |
236.200,00 |
9.448,00 |
123.1.1.1.1.6 |
Mandor |
0.02 |
OH |
206.800,00 |
4.136,00 |
123.1.1.1.1.14 |
Pekerja Terlatih |
0.16 |
OH |
150.800,00 |
24.128,00 |
123.1.1.1.1.23 |
Tukang |
0.08 |
OH |
177.500,00 |
14.200,00 |
|
|
|
|
Jumlah |
51.912,00 |
|
Bahan/Material: |
|
|
|
|
|
|
|
|
Jumlah |
0,00 |
|
Sewa Peralatan: |
|
|
|
|
117.1.1.1.22.223 |
Pabrikasi/Elektroda Baja(20%) |
0.1 |
M2 |
46.900,00 |
4.690,00 |
|
|
|
|
Jumlah |
4.690,00 |
|
|
|
|
Nilai HSPK |
56.602,00 |
| 2020 | 24.1.14.4 | Pekerjaan Besi Pipa Galvanis 1 1/4 " (Medium) | meter | 56.602,00 | Tidak Dipakai | |
189 |
NOMOR |
URAIAN KEGIATAN |
KOEF. |
SAT |
HARGA SATUAN |
HARGA |
24.4.1.4 |
Pemasangan Dinding Batu Merah 1 Pc : 5 Pp tebal 1 bata |
|
M2 |
|
|
|
Upah: |
|
|
|
|
23.2.4.1.1.2 |
Mandor |
0.03 |
Orang Hari |
196.000,00 |
5.880,00 |
23.2.4.1.2.3 |
Kepala Tukang |
0.02 |
Orang Hari |
224.000,00 |
4.480,00 |
23.2.4.1.3.4 |
Tukang |
0.2 |
Orang Hari |
168.000,00 |
33.600,00 |
23.2.4.1.4.1 |
Pembantu Tukang |
0.6 |
Orang Hari |
110.000,00 |
66.000,00 |
|
|
|
|
Jumlah |
109.960,00 |
|
Bahan/Material: |
|
|
|
|
20.1.1.2.1.3 |
Semen Portland PC @ 40 Kg |
22.2 |
Kg |
1.822,50 |
40.459,50 |
20.1.1.4.3.1 |
Pasir Pasang |
0.102 |
M3 |
225.100,00 |
22.960,20 |
20.1.1.5.6.3 |
Batu Bata Besar ( Jumbo ) |
140 |
set |
875,00 |
122.500,00 |
|
|
|
|
Jumlah |
185.919,70 |
|
Sewa Peralatan: |
|
|
|
|
|
|
|
|
Jumlah |
0,00 |
|
|
|
|
Nilai HSPK |
295.879,70 |
| 2019 | 24.4.1.4 | Pemasangan Dinding Batu Merah 1 Pc : 5 Pp tebal 1 bata | M2 | 295.879,70 | Tidak Dipakai | |
190 |
NOMOR |
URAIAN KEGIATAN |
KOEF. |
SAT |
HARGA SATUAN |
HARGA |
24.1.9.4 |
Pemasangan konstruksi gordeng kayu kelas II |
|
M3 |
|
|
|
Upah: |
|
|
|
|
123.1.1.1.1.5 |
Kepala Tukang |
2.01 |
OH |
236.200,00 |
474.762,00 |
123.1.1.1.1.6 |
Mandor |
0.335 |
OH |
206.800,00 |
69.278,00 |
123.1.1.1.1.14 |
Pekerja Terlatih |
6.7 |
OH |
150.800,00 |
1.010.359,97 |
123.1.1.1.1.23 |
Tukang |
20.1 |
OH |
177.500,00 |
3.567.750,07 |
|
|
|
|
Jumlah |
5.122.150,04 |
|
Bahan/Material: |
|
|
|
|
117.1.1.1.22.86 |
Papan/ Kaso Kayu Kelas II |
1.1 |
M3 |
14.567.300,00 |
16.024.030,35 |
117.1.1.1.22.236 |
Paku 4 inchi |
3 |
Kg |
24.100,00 |
72.300,00 |
|
|
|
|
Jumlah |
16.096.330,35 |
|
Sewa Peralatan: |
|
|
|
|
|
|
|
|
Jumlah |
0,00 |
|
|
|
|
Nilai HSPK |
21.218.480,39 |
| 2020 | 24.1.9.4 | Pemasangan konstruksi gordeng kayu kelas II | M3 | 21.218.480,39 | Tidak Dipakai | |
191 |
NOMOR |
URAIAN KEGIATAN |
KOEF. |
SAT |
HARGA SATUAN |
HARGA |
24.3.1.4 |
Lantai Kerja K-100 |
|
500 Biji |
|
|
|
Upah: |
|
|
|
|
|
|
|
|
Jumlah |
0,00 |
|
Bahan/Material: |
|
|
|
|
|
|
|
|
Jumlah |
0,00 |
|
Sewa Peralatan: |
|
|
|
|
|
|
|
|
Jumlah |
0,00 |
|
|
|
|
Nilai HSPK |
0,00 |
| 2019 | 24.3.1.4 | Lantai Kerja K-100 | 500 Biji | 0,00 | Tidak Dipakai | |
192 |
NOMOR |
URAIAN KEGIATAN |
KOEF. |
SAT |
HARGA SATUAN |
HARGA |
24.8.1.4 |
Pemasangan Paving Stone (Blok) Tbl.6 cm Abu-2 Empat Persegi Panjang |
|
10 Pcs |
|
|
|
Upah: |
|
|
|
|
|
|
|
|
Jumlah |
0,00 |
|
Bahan/Material: |
|
|
|
|
|
|
|
|
Jumlah |
0,00 |
|
Sewa Peralatan: |
|
|
|
|
|
|
|
|
Jumlah |
0,00 |
|
|
|
|
Nilai HSPK |
0,00 |
| 2019 | 24.8.1.4 | Pemasangan Paving Stone (Blok) Tbl.6 cm Abu-2 Empat Persegi Panjang | 10 Pcs | 0,00 | Tidak Dipakai | |
193 |
NOMOR |
URAIAN KEGIATAN |
KOEF. |
SAT |
HARGA SATUAN |
HARGA |
24.8.1.4 |
Pemasangan Paving Stone (Blok) Tbl.6 cm Abu-2 Empat Persegi Panjang |
|
10 Pcs |
|
|
|
Upah: |
|
|
|
|
|
|
|
|
Jumlah |
0,00 |
|
Bahan/Material: |
|
|
|
|
|
|
|
|
Jumlah |
0,00 |
|
Sewa Peralatan: |
|
|
|
|
|
|
|
|
Jumlah |
0,00 |
|
|
|
|
Nilai HSPK |
0,00 |
| 2018 | 24.8.1.4 | Pemasangan Paving Stone (Blok) Tbl.6 cm Abu-2 Empat Persegi Panjang | 10 Pcs | 0,00 | Tidak Dipakai | |
194 |
NOMOR |
URAIAN KEGIATAN |
KOEF. |
SAT |
HARGA SATUAN |
HARGA |
24.1.10.4 |
Pembuatan dan Pemasangan pintu klamp sederhana Kayu kelas III |
|
M2 |
|
|
|
Upah: |
|
|
|
|
123.1.1.1.1.5 |
Kepala Tukang |
1.05 |
OH |
236.200,00 |
248.009,99 |
123.1.1.1.1.6 |
Mandor |
0.35 |
OH |
206.800,00 |
72.380,00 |
123.1.1.1.1.14 |
Pekerja Terlatih |
0.018 |
OH |
150.800,00 |
2.714,40 |
123.1.1.1.1.23 |
Tukang |
0.105 |
OH |
177.500,00 |
18.637,50 |
|
|
|
|
Jumlah |
341.741,89 |
|
Bahan/Material: |
|
|
|
|
117.1.1.1.22.87 |
Papan/ Kaso Kayu Kelas III |
0.04 |
M3 |
6.403.200,00 |
256.127,99 |
117.1.1.1.22.233 |
Paku 2-5 inchi |
0.05 |
Kg |
34.700,00 |
1.735,00 |
|
|
|
|
Jumlah |
257.862,99 |
|
Sewa Peralatan: |
|
|
|
|
|
|
|
|
Jumlah |
0,00 |
|
|
|
|
Nilai HSPK |
599.604,88 |
| 2020 | 24.1.10.4 | Pembuatan dan Pemasangan pintu klamp sederhana Kayu kelas III | M2 | 599.604,88 | Tidak Dipakai | |
195 |
NOMOR |
URAIAN KEGIATAN |
KOEF. |
SAT |
HARGA SATUAN |
HARGA |
24.7.5.4 |
Pekerjaan Besi Pipa Galvanis 1 " (Medium) |
|
lembar |
|
|
|
Upah: |
|
|
|
|
|
|
|
|
Jumlah |
0,00 |
|
Bahan/Material: |
|
|
|
|
|
|
|
|
Jumlah |
0,00 |
|
Sewa Peralatan: |
|
|
|
|
|
|
|
|
Jumlah |
0,00 |
|
|
|
|
Nilai HSPK |
0,00 |
| 2018 | 24.7.5.4 | Pekerjaan Besi Pipa Galvanis 1 " (Medium) | lembar | 0,00 | Tidak Dipakai | |
196 |
NOMOR |
URAIAN KEGIATAN |
KOEF. |
SAT |
HARGA SATUAN |
HARGA |
24.7.5.4 |
Pekerjaan Besi Pipa Galvanis 1 " (Medium) |
|
lembar |
|
|
|
Upah: |
|
|
|
|
|
|
|
|
Jumlah |
0,00 |
|
Bahan/Material: |
|
|
|
|
|
|
|
|
Jumlah |
0,00 |
|
Sewa Peralatan: |
|
|
|
|
|
|
|
|
Jumlah |
0,00 |
|
|
|
|
Nilai HSPK |
0,00 |
| 2019 | 24.7.5.4 | Pekerjaan Besi Pipa Galvanis 1 " (Medium) | lembar | 0,00 | Tidak Dipakai | |
197 |
NOMOR |
URAIAN KEGIATAN |
KOEF. |
SAT |
HARGA SATUAN |
HARGA |
24.8.2.4 |
Biaya Menggilas dengan Mesin Gilas (Tandem) |
|
Pohon |
|
|
|
Upah: |
|
|
|
|
|
|
|
|
Jumlah |
0,00 |
|
Bahan/Material: |
|
|
|
|
|
|
|
|
Jumlah |
0,00 |
|
Sewa Peralatan: |
|
|
|
|
|
|
|
|
Jumlah |
0,00 |
|
|
|
|
Nilai HSPK |
0,00 |
| 2019 | 24.8.2.4 | Biaya Menggilas dengan Mesin Gilas (Tandem) | Pohon | 0,00 | Tidak Dipakai | |
198 |
NOMOR |
URAIAN KEGIATAN |
KOEF. |
SAT |
HARGA SATUAN |
HARGA |
24.1.13.4 |
Pekerjaan Pembuatan Pagar Besi Model PMG 1.5 m x 2,4 m |
|
panel |
|
|
|
Upah: |
|
|
|
|
123.1.1.1.1.5 |
Kepala Tukang |
0.8 |
OH |
236.200,00 |
188.960,00 |
123.1.1.1.1.6 |
Mandor |
0.4 |
OH |
206.800,00 |
82.720,00 |
123.1.1.1.1.14 |
Pekerja Terlatih |
3.2 |
OH |
150.800,00 |
482.560,01 |
123.1.1.1.1.23 |
Tukang |
1.6 |
OH |
177.500,00 |
284.000,00 |
|
|
|
|
Jumlah |
1.038.240,02 |
|
Bahan/Material: |
|
|
|
|
117.1.1.1.6.18 |
Cat Meni Besi |
0.45 |
Kg |
50.700,00 |
22.815,00 |
117.1.1.1.16.12 |
Plat Besi/Baja 244 x 122, tebal 1,8 mm |
22.608 |
Lonjor |
628.500,00 |
14.209.127,88 |
|
|
|
|
Jumlah |
14.231.942,87 |
|
Sewa Peralatan: |
|
|
|
|
117.1.1.1.22.223 |
Pabrikasi/Elektroda Baja(20%) |
3.6 |
M2 |
46.900,00 |
168.840,00 |
|
|
|
|
Jumlah |
168.840,00 |
|
|
|
|
Nilai HSPK |
15.439.022,89 |
| 2020 | 24.1.13.4 | Pekerjaan Pembuatan Pagar Besi Model PMG 1.5 m x 2,4 m | panel | 15.439.022,89 | Tidak Dipakai | |
199 |
NOMOR |
URAIAN KEGIATAN |
KOEF. |
SAT |
HARGA SATUAN |
HARGA |
24.3.2.4 |
Perbaikan Sambungan (Baut, Cincin, Pasak, dll) |
|
ikat |
|
|
|
Upah: |
|
|
|
|
|
|
|
|
Jumlah |
0,00 |
|
Bahan/Material: |
|
|
|
|
|
|
|
|
Jumlah |
0,00 |
|
Sewa Peralatan: |
|
|
|
|
|
|
|
|
Jumlah |
0,00 |
|
|
|
|
Nilai HSPK |
0,00 |
| 2018 | 24.3.2.4 | Perbaikan Sambungan (Baut, Cincin, Pasak, dll) | ikat | 0,00 | Tidak Dipakai | |
200 |
NOMOR |
URAIAN KEGIATAN |
KOEF. |
SAT |
HARGA SATUAN |
HARGA |
24.4.2.4 |
Pengecatan Genteng |
|
10 Pcs |
|
|
|
Upah: |
|
|
|
|
|
|
|
|
Jumlah |
0,00 |
|
Bahan/Material: |
|
|
|
|
|
|
|
|
Jumlah |
0,00 |
|
Sewa Peralatan: |
|
|
|
|
|
|
|
|
Jumlah |
0,00 |
|
|
|
|
Nilai HSPK |
0,00 |
| 2018 | 24.4.2.4 | Pengecatan Genteng | 10 Pcs | 0,00 | Tidak Dipakai | |