181 |
NOMOR |
KATEGORI PEKERJAAN |
URAIAN KEGIATAN |
KOEF. |
SAT |
HARGA SATUAN |
HARGA |
25.1.3.3 |
Konstruksi Jalan Paving Baru Lebar 4m (tbl. 6 cm) |
|
|
Titik |
|
|
24.1.1.7 |
- |
Pembersihan Lapangan "Ringan" dan Perataan |
0.3 |
M2 |
12.710,00 |
3.813,00 |
24.1.2.4 |
- |
Penggalian Tanah Cadas/Rabat sedalam s.d. 1 m |
0.03 |
M3 |
238.608,00 |
7.158,24 |
24.1.2.11 |
- |
Penimbunan dengan Pasir urug |
0.2 |
M3 |
471.628,02 |
94.325,61 |
24.1.2.20 |
- |
Pengangkutan Tanah keluar Proyek |
0.003 |
M3 |
166.100,00 |
498,30 |
24.1.2.22 |
- |
Penimbunan dengan Sirtu |
0.3 |
M3 |
281.590,28 |
84.477,09 |
24.1.6.22 |
- |
Plesteran Ciprat 1 Pc : 2PS |
0.2 |
M2 |
80.766,60 |
16.153,32 |
24.2.1.2 |
- |
Pemasangan Paving Blok Tbl.6 cm segi empat |
2.6 |
M2 |
116.890,00 |
303.913,99 |
24.2.1.7 |
- |
Kanstin Trap uk. 15.25.40 ; K-175 |
2.6 |
M |
127.630,24 |
331.838,62 |
24.2.1.10 |
- |
Stopper/Uskup tebal 6 cm warna |
2.32 |
M |
48.424,90 |
112.345,76 |
|
|
|
|
|
Nilai ASB |
954.523,93 |
| 2020 | 25.1.3.3.1 | Konstruksi Jalan Paving Baru Lebar 4m (tbl. 6 cm) | M | 954.523,93 | (belum diset) | |
182 |
NOMOR |
KATEGORI PEKERJAAN |
URAIAN KEGIATAN |
KOEF. |
SAT |
HARGA SATUAN |
HARGA |
25.1.3.2 |
Konstruksi Jalan Paving Baru Lebar 3m (tbl. 6 cm) |
|
|
Titik |
|
|
24.1.1.7 |
- |
Pembersihan Lapangan "Ringan" dan Perataan |
0.3 |
M2 |
12.710,00 |
3.813,00 |
24.1.2.4 |
- |
Penggalian Tanah Cadas/Rabat sedalam s.d. 1 m |
0.03 |
M3 |
238.608,00 |
7.158,24 |
24.1.2.11 |
- |
Penimbunan dengan Pasir urug |
0.2 |
M3 |
471.628,02 |
94.325,61 |
24.1.2.14 |
- |
Penimbunan Sirtu dan Pemadatan menggunakan Alat Berat |
0.3 |
M3 |
605.591,02 |
181.677,31 |
24.1.2.20 |
- |
Pengangkutan Tanah keluar Proyek |
0.003 |
M3 |
166.100,00 |
498,30 |
24.1.6.22 |
- |
Plesteran Ciprat 1 Pc : 2PS |
0.2 |
M2 |
80.766,60 |
16.153,32 |
24.2.1.2 |
- |
Pemasangan Paving Blok Tbl.6 cm segi empat |
5.7 |
M2 |
116.890,00 |
666.272,98 |
24.2.1.7 |
- |
Kanstin Trap uk. 15.25.40 ; K-175 |
2.6 |
M |
127.630,24 |
331.838,62 |
24.2.1.10 |
- |
Stopper/Uskup tebal 6 cm warna |
2.32 |
M |
48.424,90 |
112.345,76 |
|
|
|
|
|
Nilai ASB |
1.414.083,14 |
| 2020 | 25.1.3.2.1 | Konstruksi Jalan Paving Baru Lebar 3m (tbl. 6 cm) | M | 1.414.083,14 | (belum diset) | |
183 |
NOMOR |
KATEGORI PEKERJAAN |
URAIAN KEGIATAN |
KOEF. |
SAT |
HARGA SATUAN |
HARGA |
25.1.3.1 |
Konstruksi Jalan Paving Baru Lebar 2m (tbl. 6 cm) |
|
|
Titik |
|
|
24.1.1.7 |
- |
Pembersihan Lapangan "Ringan" dan Perataan |
0.2 |
M2 |
12.710,00 |
2.542,00 |
24.1.2.4 |
- |
Penggalian Tanah Cadas/Rabat sedalam s.d. 1 m |
0.03 |
M3 |
238.608,00 |
7.158,24 |
24.1.2.11 |
- |
Penimbunan dengan Pasir urug |
0.1 |
M3 |
471.628,02 |
47.162,80 |
24.1.2.20 |
- |
Pengangkutan Tanah keluar Proyek |
0.003 |
M3 |
166.100,00 |
498,30 |
24.1.2.22 |
- |
Penimbunan dengan Sirtu |
0.2 |
M3 |
281.590,28 |
56.318,06 |
24.1.6.22 |
- |
Plesteran Ciprat 1 Pc : 2PS |
0.2 |
M2 |
80.766,60 |
16.153,32 |
24.2.1.2 |
- |
Pemasangan Paving Blok Tbl.6 cm segi empat |
2.4 |
M2 |
116.890,00 |
280.536,01 |
24.2.1.7 |
- |
Kanstin Trap uk. 15.25.40 ; K-175 |
2.4 |
M |
127.630,24 |
306.312,59 |
24.2.1.10 |
- |
Stopper/Uskup tebal 6 cm warna |
2.12 |
M |
48.424,90 |
102.660,78 |
|
|
|
|
|
Nilai ASB |
819.342,11 |
| 2020 | 25.1.3.1.1 | Konstruksi Jalan Paving Baru Lebar 2m (tbl. 6 cm) | M | 819.342,11 | (belum diset) | |
184 |
NOMOR |
KATEGORI PEKERJAAN |
URAIAN KEGIATAN |
KOEF. |
SAT |
HARGA SATUAN |
HARGA |
25.1.2.1 |
Pembuatan Jalan Rigid tanpa tulangan pada jalan lingkungan |
|
|
Titik |
|
|
24.1.2.11 |
- |
Penimbunan dengan Pasir urug |
0.1 |
M3 |
471.628,02 |
47.162,80 |
24.1.4.24 |
- |
Beton mutu f'c 19,3 Mpa (K-225), slump (12±2) cm. w/c=0,58, Ready Mix |
0.15 |
M3 |
1.691.375,97 |
253.706,41 |
24.1.4.51 |
- |
Bekisting untuk Sloof |
0.3 |
M2 |
436.108,01 |
130.832,41 |
|
|
|
|
|
Nilai ASB |
431.701,62 |
| 2020 | 25.1.2.1.10 | Pembuatan Jalan Rigid tanpa tulangan pada jalan lingkungan | M2 | 431.701,62 | (belum diset) | |
185 |
NOMOR |
KATEGORI PEKERJAAN |
URAIAN KEGIATAN |
KOEF. |
SAT |
HARGA SATUAN |
HARGA |
25.1.2.1 |
Pemeliharaan Rumah Kompos Landasan Rigid |
|
|
Titik |
|
|
25.1.2.1.8 |
- |
Pembangunan Rumah Kompos Landasan Rigid |
0.3 |
M2 |
8.126.256,18 |
2.437.876,95 |
|
|
|
|
|
Nilai ASB |
2.437.876,95 |
| 2020 | 25.1.2.1.9 | Pemeliharaan Rumah Kompos Landasan Rigid | M2 | 2.437.876,95 | (belum diset) | |
186 |
NOMOR |
KATEGORI PEKERJAAN |
URAIAN KEGIATAN |
KOEF. |
SAT |
HARGA SATUAN |
HARGA |
25.1.2.1 |
Pembangunan Rumah Kompos Landasan Rigid |
|
|
Titik |
|
|
24.1.1.4 |
- |
Pengukuran dan Pembuatan Bouwplank |
0.1 |
M1 |
113.758,40 |
11.375,84 |
24.1.2.5 |
- |
Penggalian Tanah Lumpur |
0.367 |
M3 |
190.266,01 |
69.827,63 |
24.1.2.22 |
- |
Penimbunan dengan Sirtu |
0.9 |
M3 |
281.590,28 |
253.431,25 |
24.1.3.12 |
- |
Pekerjaan Pemasangan Batu Kali (1 Pc : 4 Ps) |
0.061 |
M3 |
1.390.242,02 |
84.804,76 |
24.1.3.24 |
- |
Pembuatan Lubang Strous Pile diameter 30 cm kedalaman 3 m |
0.267 |
titik |
232.058,65 |
61.959,66 |
24.1.4.23 |
- |
Beton mutu f'c 19,3 Mpa (K-225), slump (12±2) cm. w/c=0,58, dengan Molen |
0.001 |
M3 |
1.943.652,28 |
1.943,65 |
24.1.4.43 |
- |
Beton mutu f'c 31,2 Mpa (K-350), slump (12±2) cm. w/c=0,48, dengan Molen |
0.18 |
M3 |
2.201.588,97 |
396.286,03 |
24.1.4.47 |
- |
Tulangan Beton dengan besi ulir |
3.7798 |
kilogram |
23.886,93 |
90.287,81 |
24.1.4.60 |
- |
Pekerjaan Sloof Beton Bertulang (200 kg besi + Bekisting) |
0.1035 |
M3 |
7.944.915,55 |
822.298,77 |
24.1.4.64 |
- |
Pekerjaan Balok Beton Bertulang (200 kg besi + Bekisting) |
0.0012 |
M3 |
10.149.718,50 |
12.179,66 |
24.1.4.65 |
- |
Pekerjaan Balok Beton Bertulang (150 kg besi + Bekisting) |
0.033 |
M3 |
9.262.468,50 |
305.661,46 |
24.1.6.2 |
- |
Dinding Batu Merah 1 Pc : 3 Pp tebal 1 bata |
0.298 |
M2 |
336.967,11 |
100.416,20 |
24.1.6.16 |
- |
Plesteran Halus 1 Pc : 2 Ps tebal 1.5 cm |
2.99 |
M2 |
108.694,40 |
324.996,26 |
24.1.6.25 |
- |
Pemasangan acian |
2.99 |
M2 |
60.790,00 |
181.762,10 |
24.1.6.26 |
- |
Pasang Benangan 1 Pc: 2Ps |
10.5599 |
M |
40.230,50 |
424.830,06 |
24.1.7.4 |
- |
Pengecatan Kayu (1 plamir, 1 lapis cat dasar, 3 lapis cat penutup) |
6.114 |
M2 |
82.723,10 |
505.769,02 |
24.1.7.10 |
- |
Pengecatan Dasar Meni Besi |
0.039 |
M2 |
50.512,00 |
1.969,97 |
24.1.8.2 |
- |
Pemasangan Lantai Keramik 20x20 cm |
0.061 |
M2 |
486.460,50 |
29.674,09 |
24.1.8.16 |
- |
Dinding Keramik ukuran 20x25 cm |
0.122 |
M2 |
584.363,80 |
71.292,38 |
24.1.9.2 |
- |
Pemasangan Konstruksi Kuda-Kuda Konvensional Kayu Kelas II bentang 6 m. |
0.027 |
M3 |
19.216.990,36 |
518.858,75 |
24.1.9.4 |
- |
Pemasangan konstruksi gordeng kayu kelas II |
0.023 |
M3 |
21.218.480,39 |
488.025,05 |
24.1.9.15 |
- |
Pemasangan Reng /Usuk Kayu Kelas II |
5.317 |
M2 |
452.785,41 |
2.407.460,00 |
24.1.9.22 |
- |
Pemasangan Atap Sirap Asbes Tebal 4 mm |
0.16 |
M2 |
609.752,40 |
97.560,38 |
24.1.9.29 |
- |
Pemasangan Jurai Genteng Galvalume Tebal 4 mm (m) |
0.25 |
M1 |
1.159.312,51 |
289.828,13 |
24.1.9.31 |
- |
Pemasangan Listplank Kayu Kelas II |
1.933 |
M1 |
215.764,84 |
417.073,44 |
24.1.9.55 |
- |
Pemasangan Plafon Gypsum Board (120x240) 9 mm |
0.067 |
M2 |
62.325,80 |
4.175,83 |
24.1.9.57 |
- |
Pemasangan List plafond Gypsum Profil 4 " |
0.133 |
M1 |
18.304,80 |
2.434,54 |
24.1.10.14 |
- |
Pemasangan Kaca Mati tebal 5 mm |
0.002 |
M2 |
326.075,45 |
652,15 |
24.1.10.19 |
- |
Pemasangan Kunci Tanam Kecil |
0.017 |
buah |
160.354,00 |
2.726,02 |
24.1.10.23 |
- |
Pemasangan Engsel Kuningan Untuk Pintu |
0.05 |
stel |
124.695,44 |
6.234,77 |
24.1.10.40 |
- |
Pemasangan Daun Pintu PVC |
0.021 |
buah |
4.879.270,01 |
102.464,67 |
24.1.11.1 |
- |
Pemasangan Titik Stop Kontak Gedung |
0.017 |
titik |
164.792,00 |
2.801,46 |
24.1.11.2 |
- |
Pemasangan Titik Lampu Gedung |
0.067 |
titik |
164.792,00 |
11.041,06 |
24.1.12.3 |
- |
Pemasangan Dasar Saluran R.25 Segmen |
0.058 |
meter |
96.386,56 |
5.590,42 |
24.1.12.8 |
- |
Pemasangan Saluran Pipa diameter ¾'' |
0.067 |
meter |
29.478,24 |
1.975,04 |
24.1.12.13 |
- |
Pemasangan Saluran Pipa diameter 4'' |
0.084 |
meter |
68.233,88 |
5.731,65 |
24.1.12.16 |
- |
Pemasangan Kran Air |
0.033 |
buah |
89.511,00 |
2.953,86 |
24.1.14.5 |
- |
Pekerjaan Besi Pipa Galvanis 2 " (Medium) |
0.133 |
meter |
59.416,00 |
7.902,33 |
|
|
|
|
|
Nilai ASB |
8.126.256,18 |
| 2020 | 25.1.2.1.8 | Pembangunan Rumah Kompos Landasan Rigid | M2 | 8.126.256,18 | (belum diset) | |
187 |
NOMOR |
KATEGORI PEKERJAAN |
URAIAN KEGIATAN |
KOEF. |
SAT |
HARGA SATUAN |
HARGA |
25.1.2.1 |
Pemeliharaan LPS Landasan Rigid |
|
|
Titik |
|
|
25.1.2.1.6 |
- |
Pembangunan LPS Landasan Rigid |
0.3 |
M2 |
4.989.653,19 |
1.496.896,02 |
|
|
|
|
|
Nilai ASB |
1.496.896,02 |
| 2020 | 25.1.2.1.7 | Pemeliharaan LPS Landasan Rigid | M2 | 1.496.896,02 | (belum diset) | |
188 |
NOMOR |
KATEGORI PEKERJAAN |
URAIAN KEGIATAN |
KOEF. |
SAT |
HARGA SATUAN |
HARGA |
25.1.2.1 |
Pembangunan LPS Landasan Rigid |
|
|
Titik |
|
|
24.1.1.4 |
- |
Pengukuran dan Pembuatan Bouwplank |
0.148 |
M1 |
113.758,40 |
16.836,24 |
24.1.2.1 |
- |
Penggalian Tanah Biasa sedalam s.d. 1 m untuk Konstruksi |
0.074 |
M3 |
118.270,00 |
8.751,98 |
24.1.2.5 |
- |
Penggalian Tanah Lumpur |
0.128 |
M3 |
190.266,01 |
24.354,05 |
24.1.2.11 |
- |
Penimbunan dengan Pasir urug |
0.028 |
M3 |
471.628,02 |
13.205,58 |
24.1.2.22 |
- |
Penimbunan dengan Sirtu |
0.1142 |
M3 |
281.590,28 |
32.157,61 |
24.1.3.3 |
- |
Pemasangan Turap Bambu tinggi 2,75 m |
0.556 |
M1 |
565.992,31 |
314.691,72 |
24.1.3.4 |
- |
Pemasangan Crucuk Bambu 10 s/d 12 - P.3 m |
0.989 |
batang |
61.857,00 |
61.176,57 |
24.1.3.12 |
- |
Pekerjaan Pemasangan Batu Kali (1 Pc : 4 Ps) |
0.1985 |
M3 |
1.390.242,02 |
275.963,05 |
24.1.3.24 |
- |
Pembuatan Lubang Strous Pile diameter 30 cm kedalaman 3 m |
0.267 |
titik |
232.058,65 |
61.959,66 |
24.1.4.3 |
- |
Beton mutu f'c 7,4 Mpa (K-100), slump (12±2) cm. w/c=0,87, dengan Molen |
0.0755 |
M3 |
1.689.836,57 |
127.582,66 |
24.1.4.7 |
- |
Beton mutu f'c 9,8 Mpa (K-125), slump (12±2) cm. w/c=0,78, dengan Molen |
0.125 |
M3 |
1.706.080,36 |
213.260,04 |
24.1.4.43 |
- |
Beton mutu f'c 31,2 Mpa (K-350), slump (12±2) cm. w/c=0,48, dengan Molen |
0.0281 |
M3 |
2.201.588,97 |
61.864,65 |
24.1.4.47 |
- |
Tulangan Beton dengan besi ulir |
2.7815 |
kilogram |
23.886,93 |
66.441,50 |
24.1.4.60 |
- |
Pekerjaan Sloof Beton Bertulang (200 kg besi + Bekisting) |
0.023 |
M3 |
7.944.915,55 |
182.733,06 |
24.1.4.65 |
- |
Pekerjaan Balok Beton Bertulang (150 kg besi + Bekisting) |
0.048 |
M3 |
9.262.468,50 |
444.598,49 |
24.1.6.2 |
- |
Dinding Batu Merah 1 Pc : 3 Pp tebal 1 bata |
0.761 |
M2 |
336.967,11 |
256.431,96 |
24.1.6.16 |
- |
Plesteran Halus 1 Pc : 2 Ps tebal 1.5 cm |
2.335 |
M2 |
108.694,40 |
253.801,43 |
24.1.6.25 |
- |
Pemasangan acian |
1.383 |
M2 |
60.790,00 |
84.072,57 |
24.1.8.16 |
- |
Dinding Keramik ukuran 20x25 cm |
0.439 |
M2 |
584.363,80 |
256.535,72 |
24.1.9.13 |
- |
Pekerjaan Konstruksi Atap Kuda-Kuda/Gording Baja WF |
45.5 |
kilogram |
44.850,60 |
2.040.702,26 |
24.1.9.17 |
- |
Pemasang rangka atap Galvalume 0.75 |
0.737 |
M2 |
81.466,00 |
60.040,44 |
24.1.12.3 |
- |
Pemasangan Dasar Saluran R.25 Segmen |
0.12 |
meter |
96.386,56 |
11.566,39 |
24.1.12.13 |
- |
Pemasangan Saluran Pipa diameter 4'' |
0.074 |
meter |
68.233,88 |
5.049,31 |
24.2.2.70 |
- |
Pengecatan dengan Cat Road Line |
1.317 |
M2 |
87.985,00 |
115.876,25 |
|
|
|
|
|
Nilai ASB |
4.989.653,19 |
| 2020 | 25.1.2.1.6 | Pembangunan LPS Landasan Rigid | M2 | 4.989.653,19 | (belum diset) | |
189 |
NOMOR |
KATEGORI PEKERJAAN |
URAIAN KEGIATAN |
KOEF. |
SAT |
HARGA SATUAN |
HARGA |
25.1.2.1 |
Rigid Pavements Tipe A3 |
|
|
Titik |
|
|
24.1.2.3 |
- |
Penggalian Tanah Keras sedalam s.d. 1 m |
0.65 |
M3 |
157.417,60 |
102.321,44 |
24.1.2.11 |
- |
Penimbunan dengan Pasir urug |
0.0125 |
M3 |
471.628,02 |
5.895,35 |
24.1.2.22 |
- |
Penimbunan dengan Sirtu |
0.1 |
M3 |
281.590,28 |
28.159,03 |
24.1.4.1 |
- |
Beton untuk Lantai Kerja |
0.1 |
M3 |
568.825,93 |
56.882,59 |
24.1.4.43 |
- |
Beton mutu f'c 31,2 Mpa (K-350), slump (12±2) cm. w/c=0,48, dengan Molen |
0.25 |
M3 |
2.201.588,97 |
550.397,24 |
24.1.4.47 |
- |
Tulangan Beton dengan besi ulir |
1.5642 |
kilogram |
23.886,93 |
37.363,94 |
24.1.4.54 |
- |
Bekisting untuk Lantai |
0.022 |
M2 |
748.608,00 |
16.469,38 |
24.1.6.6 |
- |
Dinding Batu Merah 1 Pc : 3 Pp tebal 1/2 bata |
1 |
M2 |
162.020,00 |
162.020,00 |
24.2.1.2 |
- |
Pemasangan Paving Blok Tbl.6 cm segi empat |
0.25 |
M2 |
116.890,00 |
29.222,50 |
24.2.3.38 |
- |
Lapis Pondasi Aggregat Kelas A |
0.3 |
M3 |
908.635,51 |
272.590,67 |
24.2.3.39 |
- |
Lapis Pondasi Aggregat Kelas B |
0.4 |
M3 |
819.094,10 |
327.637,64 |
24.2.3.48 |
- |
Lapis Pondasi Aggregat Kelas C |
0.5 |
M3 |
737.720,79 |
368.860,39 |
24.2.3.83 |
- |
LasTon Lapis Aus (AC-WC) |
0.135 |
ton |
1.622.513,66 |
219.039,35 |
24.2.3.87 |
- |
LasTon Lapis Antara (AC-BC) |
0.09 |
ton |
1.502.092,25 |
135.188,31 |
24.2.3.96 |
- |
Lapis Permukaan Penetrasi Macadam |
0.05 |
M3 |
2.390.427,20 |
119.521,36 |
24.2.5.25 |
- |
Pembongkaran Beton |
0.25 |
M3 |
546.486,93 |
136.621,73 |
|
|
|
|
|
Nilai ASB |
2.568.190,93 |
| 2020 | 25.1.2.1.5 | Rigid Pavements Tipe A3 | M2 | 2.568.190,93 | (belum diset) | |
190 |
NOMOR |
KATEGORI PEKERJAAN |
URAIAN KEGIATAN |
KOEF. |
SAT |
HARGA SATUAN |
HARGA |
25.1.2.1 |
Pemeliharaan Rumah Kompos (Penggantian dengan atap baja ringan) |
|
|
Titik |
|
|
24.1.1.4 |
- |
Pengukuran dan Pembuatan Bouwplank |
0.01 |
M1 |
113.758,40 |
1.137,58 |
24.1.1.8 |
- |
Pembersihan Lapangan "Berat" dan Perataan |
1 |
M2 |
25.420,00 |
25.420,00 |
24.1.2.1 |
- |
Penggalian Tanah Biasa sedalam s.d. 1 m untuk Konstruksi |
0.375 |
M3 |
118.270,00 |
44.351,25 |
24.1.2.22 |
- |
Penimbunan dengan Sirtu |
0.23 |
M3 |
281.590,28 |
64.765,77 |
24.1.4.47 |
- |
Tulangan Beton dengan besi ulir |
33.33 |
kilogram |
23.886,93 |
796.151,40 |
24.1.5.1 |
- |
Pekerjaan Perakitan dan Pemasangan Struktur Besi/Baja Profil |
13 |
kilogram |
40.446,50 |
525.804,50 |
24.1.5.2 |
- |
Pekerjaan Pengelasan dengan las listrik |
41 |
cm |
37.096,20 |
1.520.944,17 |
24.1.5.11 |
- |
Pekerjaan Pemasangan Baut Mur Baja |
1.33 |
kilogram |
34.200,60 |
45.486,80 |
24.1.6.3 |
- |
Dinding Batu Merah 1 Pc : 4 Pp tebal 1 bata |
0.083 |
M2 |
320.687,30 |
26.617,05 |
24.1.7.8 |
- |
Pengecatan Besi |
1.83 |
M2 |
53.052,00 |
97.085,16 |
24.1.9.17 |
- |
Pemasang rangka atap Galvalume 0.75 |
0.35 |
M2 |
81.466,00 |
28.513,10 |
24.2.1.2 |
- |
Pemasangan Paving Blok Tbl.6 cm segi empat |
1.104 |
M2 |
116.890,00 |
129.046,56 |
24.2.1.9 |
- |
Stopper/Uskup tebal 8 cm abu - abu |
0.67 |
M |
53.100,90 |
35.577,60 |
|
|
|
|
|
Nilai ASB |
3.340.900,93 |
| 2020 | 25.1.2.1.4 | Pemeliharaan Rumah Kompos (Penggantian dengan atap baja ringan) | M2 | 3.340.900,93 | (belum diset) | |
191 |
NOMOR |
KATEGORI PEKERJAAN |
URAIAN KEGIATAN |
KOEF. |
SAT |
HARGA SATUAN |
HARGA |
25.1.2.1 |
Pembangunan Rumah Kompos Rangka Baja Ringan |
|
|
Titik |
|
|
24.1.1.4 |
- |
Pengukuran dan Pembuatan Bouwplank |
0.01 |
M1 |
113.758,40 |
1.137,58 |
24.1.1.8 |
- |
Pembersihan Lapangan "Berat" dan Perataan |
1 |
M2 |
25.420,00 |
25.420,00 |
24.1.2.1 |
- |
Penggalian Tanah Biasa sedalam s.d. 1 m untuk Konstruksi |
0.375 |
M3 |
118.270,00 |
44.351,25 |
24.1.2.9 |
- |
Penimbunan kembali Tanah Galian |
0.0588 |
M3 |
85.740,00 |
5.041,51 |
24.1.2.22 |
- |
Penimbunan dengan Sirtu |
0.23 |
M3 |
281.590,28 |
64.765,77 |
24.1.3.23 |
- |
Pembuatan Lubang Strous Pile diameter 20 cm kedalaman 3 m |
0.1875 |
titik |
193.385,05 |
36.259,70 |
24.1.3.25 |
- |
Pemakaian Spesi Campuran Strous Pile (1 Pc : 1,5 Ps : 2,5 Kr) |
0.012 |
M3 |
1.054.854,31 |
12.658,25 |
24.1.4.3 |
- |
Beton mutu f'c 7,4 Mpa (K-100), slump (12±2) cm. w/c=0,87, dengan Molen |
0.055 |
M3 |
1.689.836,57 |
92.941,01 |
24.1.4.47 |
- |
Tulangan Beton dengan besi ulir |
33.33 |
kilogram |
23.886,93 |
796.151,40 |
24.1.4.51 |
- |
Bekisting untuk Sloof |
1.17 |
M2 |
436.108,01 |
510.246,35 |
24.1.5.1 |
- |
Pekerjaan Perakitan dan Pemasangan Struktur Besi/Baja Profil |
0.67 |
kilogram |
40.446,50 |
27.099,16 |
24.1.5.2 |
- |
Pekerjaan Pengelasan dengan las listrik |
2.4 |
cm |
37.096,20 |
89.030,88 |
24.1.5.8 |
- |
Perbaikan Sambungan (Baut, Cincin, Pasak, dll) |
0.271 |
kilogram |
36.633,00 |
9.927,54 |
24.1.5.9 |
- |
Perbaikan dan Penggantian Baja Struktural (profil) |
0.92 |
kilogram |
22.050,90 |
20.286,83 |
24.1.5.11 |
- |
Pekerjaan Pemasangan Baut Mur Baja |
1.33 |
kilogram |
34.200,60 |
45.486,80 |
24.1.6.3 |
- |
Dinding Batu Merah 1 Pc : 4 Pp tebal 1 bata |
0.083 |
M2 |
320.687,30 |
26.617,05 |
24.1.6.18 |
- |
Plesteran Halus 1 Pc : 4 Ps tebal 1.5 cm |
1.8 |
M2 |
99.416,60 |
178.949,88 |
24.1.6.25 |
- |
Pemasangan acian |
1.8 |
M2 |
60.790,00 |
109.422,00 |
24.1.6.26 |
- |
Pasang Benangan 1 Pc: 2Ps |
1.42 |
M |
40.230,50 |
57.127,31 |
24.1.7.8 |
- |
Pengecatan Besi |
1.8 |
M2 |
53.052,00 |
95.493,60 |
24.1.7.10 |
- |
Pengecatan Dasar Meni Besi |
1.83 |
M2 |
50.512,00 |
92.436,96 |
24.1.9.17 |
- |
Pemasang rangka atap Galvalume 0.75 |
0.35 |
M2 |
81.466,00 |
28.513,10 |
24.1.10.37 |
- |
Pemasangan Kawat Harmonika |
1.17 |
M2 |
155.487,14 |
181.919,95 |
24.1.14.5 |
- |
Pekerjaan Besi Pipa Galvanis 2 " (Medium) |
0.146 |
meter |
59.416,00 |
8.674,74 |
24.2.1.2 |
- |
Pemasangan Paving Blok Tbl.6 cm segi empat |
1.104 |
M2 |
116.890,00 |
129.046,56 |
24.2.1.6 |
- |
Kanstin BDCM 21.5 |
0.42 |
M |
121.117,38 |
50.869,30 |
24.2.1.9 |
- |
Stopper/Uskup tebal 8 cm abu - abu |
0.67 |
M |
53.100,90 |
35.577,60 |
|
|
|
|
|
Nilai ASB |
2.775.452,06 |
| 2020 | 25.1.2.1.3 | Pembangunan Rumah Kompos Rangka Baja Ringan | M2 | 2.775.452,06 | (belum diset) | |
192 |
NOMOR |
KATEGORI PEKERJAAN |
URAIAN KEGIATAN |
KOEF. |
SAT |
HARGA SATUAN |
HARGA |
25.1.2.1 |
Rigid Pavements Tipe A2 |
|
|
Titik |
|
|
24.1.2.3 |
- |
Penggalian Tanah Keras sedalam s.d. 1 m |
0.7 |
M3 |
157.417,60 |
110.192,32 |
24.1.2.11 |
- |
Penimbunan dengan Pasir urug |
0.0125 |
M3 |
471.628,02 |
5.895,35 |
24.1.2.14 |
- |
Penimbunan Sirtu dan Pemadatan menggunakan Alat Berat |
0.1 |
M3 |
605.591,02 |
60.559,10 |
24.1.4.1 |
- |
Beton untuk Lantai Kerja |
0.1 |
M3 |
568.825,93 |
56.882,59 |
24.1.4.43 |
- |
Beton mutu f'c 31,2 Mpa (K-350), slump (12±2) cm. w/c=0,48, dengan Molen |
0.3 |
M3 |
2.201.588,97 |
660.476,72 |
24.1.4.47 |
- |
Tulangan Beton dengan besi ulir |
1.877 |
kilogram |
23.886,93 |
44.835,77 |
24.1.4.54 |
- |
Bekisting untuk Lantai |
0.022 |
M2 |
748.608,00 |
16.469,38 |
24.1.6.6 |
- |
Dinding Batu Merah 1 Pc : 3 Pp tebal 1/2 bata |
1 |
M2 |
162.020,00 |
162.020,00 |
24.2.1.2 |
- |
Pemasangan Paving Blok Tbl.6 cm segi empat |
0.25 |
M2 |
116.890,00 |
29.222,50 |
24.2.1.6 |
- |
Kanstin BDCM 21.5 |
0.3333 |
M |
121.117,38 |
40.368,42 |
24.2.3.38 |
- |
Lapis Pondasi Aggregat Kelas A |
0.3 |
M3 |
908.635,51 |
272.590,67 |
24.2.3.39 |
- |
Lapis Pondasi Aggregat Kelas B |
0.4 |
M3 |
819.094,10 |
327.637,64 |
24.2.3.48 |
- |
Lapis Pondasi Aggregat Kelas C |
0.5 |
M3 |
737.720,79 |
368.860,39 |
24.2.3.83 |
- |
LasTon Lapis Aus (AC-WC) |
0.135 |
ton |
1.622.513,66 |
219.039,35 |
24.2.3.87 |
- |
LasTon Lapis Antara (AC-BC) |
0.09 |
ton |
1.502.092,25 |
135.188,31 |
24.2.3.97 |
- |
Lapis Pondasi/Perata Penetrasi Macadam |
0.5 |
M3 |
2.520.503,24 |
1.260.251,62 |
24.2.5.25 |
- |
Pembongkaran Beton |
0.3 |
M3 |
546.486,93 |
163.946,09 |
|
|
|
|
|
Nilai ASB |
3.934.436,22 |
| 2020 | 25.1.2.1.2 | Rigid Pavements Tipe A2 | M2 | 3.934.436,22 | (belum diset) | |
193 |
NOMOR |
KATEGORI PEKERJAAN |
URAIAN KEGIATAN |
KOEF. |
SAT |
HARGA SATUAN |
HARGA |
25.1.2.1 |
Rigid Pavements Tipe A1 |
|
|
Titik |
|
|
24.1.2.3 |
- |
Penggalian Tanah Keras sedalam s.d. 1 m |
0.75 |
M3 |
157.417,60 |
118.063,20 |
24.1.2.11 |
- |
Penimbunan dengan Pasir urug |
0.0125 |
M3 |
471.628,02 |
5.895,35 |
24.1.2.14 |
- |
Penimbunan Sirtu dan Pemadatan menggunakan Alat Berat |
0.1 |
M3 |
605.591,02 |
60.559,10 |
24.1.4.1 |
- |
Beton untuk Lantai Kerja |
0.1 |
M3 |
568.825,93 |
56.882,59 |
24.1.4.43 |
- |
Beton mutu f'c 31,2 Mpa (K-350), slump (12±2) cm. w/c=0,48, dengan Molen |
0.35 |
M3 |
2.201.588,97 |
770.556,13 |
24.1.4.47 |
- |
Tulangan Beton dengan besi ulir |
2.19 |
kilogram |
23.886,93 |
52.312,38 |
24.1.4.54 |
- |
Bekisting untuk Lantai |
0.022 |
M2 |
748.608,00 |
16.469,38 |
24.1.6.6 |
- |
Dinding Batu Merah 1 Pc : 3 Pp tebal 1/2 bata |
1 |
M2 |
162.020,00 |
162.020,00 |
24.2.1.2 |
- |
Pemasangan Paving Blok Tbl.6 cm segi empat |
0.25 |
M2 |
116.890,00 |
29.222,50 |
24.2.1.6 |
- |
Kanstin BDCM 21.5 |
0.3333 |
M |
121.117,38 |
40.368,42 |
24.2.3.38 |
- |
Lapis Pondasi Aggregat Kelas A |
0.3 |
M3 |
908.635,51 |
272.590,67 |
24.2.3.39 |
- |
Lapis Pondasi Aggregat Kelas B |
0.4 |
M3 |
819.094,10 |
327.637,64 |
24.2.3.48 |
- |
Lapis Pondasi Aggregat Kelas C |
0.5 |
M3 |
737.720,79 |
368.860,39 |
24.2.3.83 |
- |
LasTon Lapis Aus (AC-WC) |
0.135 |
ton |
1.622.513,66 |
219.039,35 |
24.2.3.87 |
- |
LasTon Lapis Antara (AC-BC) |
0.09 |
ton |
1.502.092,25 |
135.188,31 |
24.2.3.97 |
- |
Lapis Pondasi/Perata Penetrasi Macadam |
0.05 |
M3 |
2.520.503,24 |
126.025,16 |
24.2.5.25 |
- |
Pembongkaran Beton |
0.35 |
M3 |
546.486,93 |
191.270,42 |
|
|
|
|
|
Nilai ASB |
2.952.961,00 |
| 2020 | 25.1.2.1.1 | Rigid Pavements Tipe A1 | M2 | 2.952.961,00 | (belum diset) | |
194 |
NOMOR |
KATEGORI PEKERJAAN |
URAIAN KEGIATAN |
KOEF. |
SAT |
HARGA SATUAN |
HARGA |
25.1.1.2 |
Pemeliharaan Jalan Overlay Lebar 20 m |
|
|
Titik |
|
|
25.1.1.2.4 |
- |
Pemeliharaan Jalan Overlay |
20 |
M2 |
640.512,49 |
12.810.249,76 |
|
|
|
|
|
Nilai ASB |
12.810.249,76 |
| 2020 | 25.1.1.2.34 | Pemeliharaan Jalan Overlay Lebar 20 m | M1 | 12.810.249,76 | (belum diset) | |
195 |
NOMOR |
KATEGORI PEKERJAAN |
URAIAN KEGIATAN |
KOEF. |
SAT |
HARGA SATUAN |
HARGA |
25.1.1.2 |
Pemeliharaan Jalan Overlay Lebar 18 m |
|
|
Titik |
|
|
25.1.1.2.4 |
- |
Pemeliharaan Jalan Overlay |
18 |
M2 |
640.512,49 |
11.529.224,79 |
|
|
|
|
|
Nilai ASB |
11.529.224,79 |
| 2020 | 25.1.1.2.33 | Pemeliharaan Jalan Overlay Lebar 18 m | M1 | 11.529.224,79 | (belum diset) | |
196 |
NOMOR |
KATEGORI PEKERJAAN |
URAIAN KEGIATAN |
KOEF. |
SAT |
HARGA SATUAN |
HARGA |
25.1.1.2 |
Pemeliharaan Jalan Overlay Lebar 17,5 m |
|
|
Titik |
|
|
25.1.1.2.4 |
- |
Pemeliharaan Jalan Overlay |
17.5 |
M2 |
640.512,49 |
11.208.968,54 |
|
|
|
|
|
Nilai ASB |
11.208.968,54 |
| 2020 | 25.1.1.2.32 | Pemeliharaan Jalan Overlay Lebar 17,5 m | M1 | 11.208.968,54 | (belum diset) | |
197 |
NOMOR |
KATEGORI PEKERJAAN |
URAIAN KEGIATAN |
KOEF. |
SAT |
HARGA SATUAN |
HARGA |
25.1.1.2 |
Pemeliharaan Jalan Overlay Lebar 17 m |
|
|
Titik |
|
|
25.1.1.2.4 |
- |
Pemeliharaan Jalan Overlay |
17 |
M2 |
640.512,49 |
10.888.712,30 |
|
|
|
|
|
Nilai ASB |
10.888.712,30 |
| 2020 | 25.1.1.2.31 | Pemeliharaan Jalan Overlay Lebar 17 m | M1 | 10.888.712,30 | (belum diset) | |
198 |
NOMOR |
KATEGORI PEKERJAAN |
URAIAN KEGIATAN |
KOEF. |
SAT |
HARGA SATUAN |
HARGA |
25.1.1.2 |
Pemeliharaan Jalan Overlay Lebar 16,5 m |
|
|
Titik |
|
|
25.1.1.2.4 |
- |
Pemeliharaan Jalan Overlay |
16.5 |
M2 |
640.512,49 |
10.568.456,05 |
|
|
|
|
|
Nilai ASB |
10.568.456,05 |
| 2020 | 25.1.1.2.30 | Pemeliharaan Jalan Overlay Lebar 16,5 m | M1 | 10.568.456,05 | (belum diset) | |
199 |
NOMOR |
KATEGORI PEKERJAAN |
URAIAN KEGIATAN |
KOEF. |
SAT |
HARGA SATUAN |
HARGA |
25.1.1.2 |
Pemeliharaan Jalan Overlay Lebar 16 m |
|
|
Titik |
|
|
25.1.1.2.4 |
- |
Pemeliharaan Jalan Overlay |
16 |
M2 |
640.512,49 |
10.248.199,81 |
|
|
|
|
|
Nilai ASB |
10.248.199,81 |
| 2020 | 25.1.1.2.29 | Pemeliharaan Jalan Overlay Lebar 16 m | M1 | 10.248.199,81 | (belum diset) | |
200 |
NOMOR |
KATEGORI PEKERJAAN |
URAIAN KEGIATAN |
KOEF. |
SAT |
HARGA SATUAN |
HARGA |
25.1.1.2 |
Pemeliharaan Jalan Overlay Lebar 15,5 m |
|
|
Titik |
|
|
25.1.1.2.4 |
- |
Pemeliharaan Jalan Overlay |
15.5 |
M2 |
640.512,49 |
9.927.943,57 |
|
|
|
|
|
Nilai ASB |
9.927.943,57 |
| 2020 | 25.1.1.2.28 | Pemeliharaan Jalan Overlay Lebar 15,5 m | M1 | 9.927.943,57 | (belum diset) | |