41 |
NOMOR |
KATEGORI PEKERJAAN |
URAIAN KEGIATAN |
KOEF. |
SAT |
HARGA SATUAN |
HARGA |
25.1.1.2 |
Pemeliharaan Jalan Overlay Lebar 17 m |
|
|
Titik |
|
|
25.1.1.2.4 |
- |
Pemeliharaan Jalan Overlay |
17 |
M2 |
640.512,49 |
10.888.712,30 |
|
|
|
|
|
Nilai ASB |
10.888.712,30 |
| 2020 | 25.1.1.2.31 | Pemeliharaan Jalan Overlay Lebar 17 m | M1 | 10.888.712,30 | (belum diset) | |
42 |
NOMOR |
KATEGORI PEKERJAAN |
URAIAN KEGIATAN |
KOEF. |
SAT |
HARGA SATUAN |
HARGA |
25.1.1.2 |
Pemeliharaan Jalan Overlay Lebar 16,5 m |
|
|
Titik |
|
|
25.1.1.2.4 |
- |
Pemeliharaan Jalan Overlay |
16.5 |
M2 |
640.512,49 |
10.568.456,05 |
|
|
|
|
|
Nilai ASB |
10.568.456,05 |
| 2020 | 25.1.1.2.30 | Pemeliharaan Jalan Overlay Lebar 16,5 m | M1 | 10.568.456,05 | (belum diset) | |
43 |
NOMOR |
KATEGORI PEKERJAAN |
URAIAN KEGIATAN |
KOEF. |
SAT |
HARGA SATUAN |
HARGA |
25.1.1.2 |
Pemeliharaan Jalan Overlay Lebar 16 m |
|
|
Titik |
|
|
25.1.1.2.4 |
- |
Pemeliharaan Jalan Overlay |
16 |
M2 |
640.512,49 |
10.248.199,81 |
|
|
|
|
|
Nilai ASB |
10.248.199,81 |
| 2020 | 25.1.1.2.29 | Pemeliharaan Jalan Overlay Lebar 16 m | M1 | 10.248.199,81 | (belum diset) | |
44 |
NOMOR |
KATEGORI PEKERJAAN |
URAIAN KEGIATAN |
KOEF. |
SAT |
HARGA SATUAN |
HARGA |
27.1.1.6 |
Pemasangan Lampu HPS 150 W - 1 Phase - Ornamen 3 m |
|
|
Titik |
|
|
24.2.2.1 |
- |
Pemasangan Konektor Kabel |
2 |
buah |
1.661,45 |
3.322,90 |
24.2.2.14 |
- |
Pemasangan / Penarikan Kabel NFA2X (Twisted) 4 x 16 mm |
50 |
M |
32.059,81 |
1.602.990,50 |
24.2.2.17 |
- |
Instalasi 1 Titik Lampu PJU (Tarikan Udara) 4 m |
1 |
M |
2.350.359,81 |
2.350.359,81 |
24.2.2.26 |
- |
Pemasangan Ornamen Lampu PJU panjang 3m |
1 |
buah |
3.313.930,00 |
3.313.930,00 |
24.2.2.28 |
- |
Perakitan dan Pemasangan Panel Lampu PJU - 1 Phase 2200VA |
0.1 |
unit |
1.636.566,95 |
163.656,70 |
24.2.2.40 |
- |
Pemasangan Panel Meter 1 Phase |
0.1 |
unit |
288.360,00 |
28.836,00 |
24.2.2.43 |
- |
Pemasangan Lampu HPS 150 W/220 V Lengkap Armateur, Balast, Ignitor & Capasitor |
1 |
unit |
2.642.075,00 |
2.642.075,00 |
|
|
|
|
|
Nilai ASB |
10.105.170,91 |
| 2020 | 27.1.1.6.1 | Pemasangan Lampu HPS 150 W - 1 Phase - Ornamen 3 m | titik | 10.105.170,91 | (belum diset) | |
45 |
NOMOR |
KATEGORI PEKERJAAN |
URAIAN KEGIATAN |
KOEF. |
SAT |
HARGA SATUAN |
HARGA |
25.1.1.2 |
Pemeliharaan Jalan Overlay Lebar 15,5 m |
|
|
Titik |
|
|
25.1.1.2.4 |
- |
Pemeliharaan Jalan Overlay |
15.5 |
M2 |
640.512,49 |
9.927.943,57 |
|
|
|
|
|
Nilai ASB |
9.927.943,57 |
| 2020 | 25.1.1.2.28 | Pemeliharaan Jalan Overlay Lebar 15,5 m | M1 | 9.927.943,57 | (belum diset) | |
46 |
NOMOR |
KATEGORI PEKERJAAN |
URAIAN KEGIATAN |
KOEF. |
SAT |
HARGA SATUAN |
HARGA |
25.1.1.2 |
Pemeliharaan Jalan Overlay Lebar 15 m |
|
|
Titik |
|
|
25.1.1.2.4 |
- |
Pemeliharaan Jalan Overlay |
15 |
M2 |
640.512,49 |
9.607.687,32 |
|
|
|
|
|
Nilai ASB |
9.607.687,32 |
| 2020 | 25.1.1.2.27 | Pemeliharaan Jalan Overlay Lebar 15 m | M1 | 9.607.687,32 | (belum diset) | |
47 |
NOMOR |
KATEGORI PEKERJAAN |
URAIAN KEGIATAN |
KOEF. |
SAT |
HARGA SATUAN |
HARGA |
25.3.2.8 |
Saluran Batu kali 100/120 + Tutup Pelat (2 sisi) |
|
|
Titik |
|
|
24.1.2.1 |
- |
Penggalian Tanah Biasa sedalam s.d. 1 m untuk Konstruksi |
8.6 |
M3 |
118.270,00 |
1.017.122,05 |
24.1.2.9 |
- |
Penimbunan kembali Tanah Galian |
0.6 |
M3 |
85.740,00 |
51.444,00 |
24.1.2.11 |
- |
Penimbunan dengan Pasir urug |
1.4 |
M3 |
471.628,02 |
660.279,21 |
24.1.2.20 |
- |
Pengangkutan Tanah keluar Proyek |
8 |
M3 |
166.100,00 |
1.328.800,00 |
24.1.3.12 |
- |
Pekerjaan Pemasangan Batu Kali (1 Pc : 4 Ps) |
3.6 |
M3 |
1.390.242,02 |
5.004.871,13 |
24.1.4.23 |
- |
Beton mutu f'c 19,3 Mpa (K-225), slump (12±2) cm. w/c=0,58, dengan Molen |
0.2 |
M3 |
1.943.652,28 |
388.730,46 |
24.1.6.18 |
- |
Plesteran Halus 1 Pc : 4 Ps tebal 1.5 cm |
6.4 |
M2 |
99.416,60 |
636.266,26 |
24.1.6.26 |
- |
Pasang Benangan 1 Pc: 2Ps |
4 |
M |
40.230,50 |
160.922,00 |
24.1.12.5 |
- |
Pemasangan Dasar Saluran R.15 (1/2 lingkaran) |
2 |
meter |
105.933,20 |
211.866,40 |
24.1.12.20 |
- |
Pemasangan Lubang Drainase |
4 |
buah |
22.941,10 |
91.764,40 |
|
|
|
|
|
Nilai ASB |
9.552.065,91 |
| 2020 | 25.3.2.8.1 | Saluran Batu kali 100/120 + Tutup Pelat (2 sisi) | M | 9.552.065,91 | (belum diset) | |
48 |
NOMOR |
KATEGORI PEKERJAAN |
URAIAN KEGIATAN |
KOEF. |
SAT |
HARGA SATUAN |
HARGA |
25.3.6.2 |
Saluran Tipe A |
|
|
Titik |
|
|
24.1.2.1 |
- |
Penggalian Tanah Biasa sedalam s.d. 1 m untuk Konstruksi |
8.6 |
M3 |
118.270,00 |
1.017.122,05 |
24.1.2.9 |
- |
Penimbunan kembali Tanah Galian |
0.6 |
M3 |
85.740,00 |
51.444,00 |
24.1.2.11 |
- |
Penimbunan dengan Pasir urug |
1.4 |
M3 |
471.628,02 |
660.279,21 |
24.1.2.20 |
- |
Pengangkutan Tanah keluar Proyek |
8 |
M3 |
166.100,00 |
1.328.800,00 |
24.1.3.12 |
- |
Pekerjaan Pemasangan Batu Kali (1 Pc : 4 Ps) |
3.6 |
M3 |
1.390.242,02 |
5.004.871,13 |
24.1.4.23 |
- |
Beton mutu f'c 19,3 Mpa (K-225), slump (12±2) cm. w/c=0,58, dengan Molen |
0.2 |
M3 |
1.943.652,28 |
388.730,46 |
24.1.6.18 |
- |
Plesteran Halus 1 Pc : 4 Ps tebal 1.5 cm |
6.4 |
M2 |
99.416,60 |
636.266,26 |
24.1.6.26 |
- |
Pasang Benangan 1 Pc: 2Ps |
4 |
M |
40.230,50 |
160.922,00 |
24.1.12.5 |
- |
Pemasangan Dasar Saluran R.15 (1/2 lingkaran) |
2 |
meter |
105.933,20 |
211.866,40 |
24.1.12.20 |
- |
Pemasangan Lubang Drainase |
4 |
buah |
22.941,10 |
91.764,40 |
|
|
|
|
|
Nilai ASB |
9.552.065,91 |
| 2020 | 25.3.6.2.1 | Saluran Tipe A | M | 9.552.065,91 | (belum diset) | |
49 |
NOMOR |
KATEGORI PEKERJAAN |
URAIAN KEGIATAN |
KOEF. |
SAT |
HARGA SATUAN |
HARGA |
28.2.1.2 |
Tandon Air Kebakaran |
|
|
Titik |
|
|
24.1.1.4 |
- |
Pengukuran dan Pembuatan Bouwplank |
0.2875 |
M1 |
113.758,40 |
32.705,54 |
24.1.2.1 |
- |
Penggalian Tanah Biasa sedalam s.d. 1 m untuk Konstruksi |
3.065 |
M3 |
118.270,00 |
362.497,56 |
24.1.2.9 |
- |
Penimbunan kembali Tanah Galian |
0.536 |
M3 |
85.740,00 |
45.956,64 |
24.1.2.17 |
- |
Pengangkutan Tanah dari Lubang Galian yg dalamnya > 1 m |
1.2861 |
M3 |
40.285,00 |
51.810,54 |
24.1.2.22 |
- |
Penimbunan dengan Sirtu |
0.122 |
M3 |
281.590,28 |
34.354,01 |
24.1.3.3 |
- |
Pemasangan Turap Bambu tinggi 2,75 m |
3.015 |
M1 |
565.992,31 |
1.706.466,86 |
24.1.4.3 |
- |
Beton mutu f'c 7,4 Mpa (K-100), slump (12±2) cm. w/c=0,87, dengan Molen |
0.0657 |
M3 |
1.689.836,57 |
111.022,27 |
24.1.4.47 |
- |
Tulangan Beton dengan besi ulir |
2.428 |
kilogram |
23.886,93 |
57.997,46 |
24.1.4.60 |
- |
Pekerjaan Sloof Beton Bertulang (200 kg besi + Bekisting) |
0.6918 |
M3 |
7.944.915,55 |
5.496.292,56 |
24.1.4.65 |
- |
Pekerjaan Balok Beton Bertulang (150 kg besi + Bekisting) |
0.14 |
M3 |
9.262.468,50 |
1.296.745,60 |
24.1.6.18 |
- |
Plesteran Halus 1 Pc : 4 Ps tebal 1.5 cm |
0.89 |
M2 |
99.416,60 |
88.480,77 |
24.1.6.26 |
- |
Pasang Benangan 1 Pc: 2Ps |
4.11 |
M |
40.230,50 |
165.347,36 |
24.1.12.13 |
- |
Pemasangan Saluran Pipa diameter 4'' |
0.07 |
meter |
68.233,88 |
4.776,37 |
24.2.2.70 |
- |
Pengecatan dengan Cat Road Line |
0.057 |
M2 |
87.985,00 |
5.015,15 |
|
|
|
|
|
Nilai ASB |
9.459.468,69 |
| 2020 | 28.2.1.2.1 | Tandon Air Kebakaran | M3 | 9.459.468,69 | (belum diset) | |
50 |
NOMOR |
KATEGORI PEKERJAAN |
URAIAN KEGIATAN |
KOEF. |
SAT |
HARGA SATUAN |
HARGA |
25.1.1.2 |
Pemeliharaan Jalan Overlay Lebar 14,5 m |
|
|
Titik |
|
|
25.1.1.2.4 |
- |
Pemeliharaan Jalan Overlay |
14.5 |
M2 |
640.512,49 |
9.287.431,08 |
|
|
|
|
|
Nilai ASB |
9.287.431,08 |
| 2020 | 25.1.1.2.26 | Pemeliharaan Jalan Overlay Lebar 14,5 m | M1 | 9.287.431,08 | (belum diset) | |
51 |
NOMOR |
KATEGORI PEKERJAAN |
URAIAN KEGIATAN |
KOEF. |
SAT |
HARGA SATUAN |
HARGA |
25.1.1.2 |
Pemeliharaan Jalan Overlay Lebar 14 m |
|
|
Titik |
|
|
25.1.1.2.4 |
- |
Pemeliharaan Jalan Overlay |
14 |
M2 |
640.512,49 |
8.967.174,83 |
|
|
|
|
|
Nilai ASB |
8.967.174,83 |
| 2020 | 25.1.1.2.25 | Pemeliharaan Jalan Overlay Lebar 14 m | M1 | 8.967.174,83 | (belum diset) | |
52 |
NOMOR |
KATEGORI PEKERJAAN |
URAIAN KEGIATAN |
KOEF. |
SAT |
HARGA SATUAN |
HARGA |
27.1.1.11 |
Pemasangan Lampu HPS 250 W - 1 Phase - Ornamen 6 m |
|
|
Titik |
|
|
24.2.2.1 |
- |
Pemasangan Konektor Kabel |
2 |
buah |
1.661,45 |
3.322,90 |
24.2.2.14 |
- |
Pemasangan / Penarikan Kabel NFA2X (Twisted) 4 x 16 mm |
50 |
M |
32.059,81 |
1.602.990,50 |
24.2.2.18 |
- |
Intalasi 1 Titik Lampu PJU (Tarikan Udara) 7,5 m |
1 |
M |
4.400.309,81 |
4.400.309,81 |
24.2.2.27 |
- |
Pemasangan Ornamen Lampu PJU panjang 6m |
1 |
buah |
2.381.047,52 |
2.381.047,52 |
24.2.2.28 |
- |
Perakitan dan Pemasangan Panel Lampu PJU - 1 Phase 2200VA |
0.1 |
unit |
1.636.566,95 |
163.656,70 |
24.2.2.40 |
- |
Pemasangan Panel Meter 1 Phase |
0.1 |
unit |
288.360,00 |
28.836,00 |
24.2.2.44 |
- |
Pemasangan Lampu HPS 250 W/220 V Lengkap Armateur, Balast, Ignitor & Capasitor |
1 |
unit |
218.975,00 |
218.975,00 |
|
|
|
|
|
Nilai ASB |
8.799.138,43 |
| 2020 | 27.1.1.11.1 | Pemasangan Lampu HPS 250 W - 1 Phase - Ornamen 6 m | titik | 8.799.138,43 | (belum diset) | |
53 |
NOMOR |
KATEGORI PEKERJAAN |
URAIAN KEGIATAN |
KOEF. |
SAT |
HARGA SATUAN |
HARGA |
27.1.1.15 |
Pemasangan Lampu HPS 400 W - 1 Phase - Ornamen 6 m |
|
|
Titik |
|
|
24.2.2.1 |
- |
Pemasangan Konektor Kabel |
2 |
buah |
1.661,45 |
3.322,90 |
24.2.2.14 |
- |
Pemasangan / Penarikan Kabel NFA2X (Twisted) 4 x 16 mm |
50 |
M |
32.059,81 |
1.602.990,50 |
24.2.2.18 |
- |
Intalasi 1 Titik Lampu PJU (Tarikan Udara) 7,5 m |
1 |
M |
4.400.309,81 |
4.400.309,81 |
24.2.2.27 |
- |
Pemasangan Ornamen Lampu PJU panjang 6m |
1 |
buah |
2.381.047,52 |
2.381.047,52 |
24.2.2.28 |
- |
Perakitan dan Pemasangan Panel Lampu PJU - 1 Phase 2200VA |
0.1 |
unit |
1.636.566,95 |
163.656,70 |
24.2.2.40 |
- |
Pemasangan Panel Meter 1 Phase |
0.1 |
unit |
288.360,00 |
28.836,00 |
24.2.2.45 |
- |
Pemasangan Lampu HPS 400 W/220 V Lengkap Armateur, Balast, Ignitor & Capasitor |
1 |
unit |
218.975,00 |
218.975,00 |
|
|
|
|
|
Nilai ASB |
8.799.138,43 |
| 2020 | 27.1.1.15.1 | Pemasangan Lampu HPS 400 W - 1 Phase - Ornamen 6 m | lipat | 8.799.138,43 | (belum diset) | |
54 |
NOMOR |
KATEGORI PEKERJAAN |
URAIAN KEGIATAN |
KOEF. |
SAT |
HARGA SATUAN |
HARGA |
25.1.1.2 |
Pemeliharaan Jalan Overlay Lebar 13,5 m |
|
|
Titik |
|
|
25.1.1.2.4 |
- |
Pemeliharaan Jalan Overlay |
13.5 |
M2 |
640.512,49 |
8.646.918,59 |
|
|
|
|
|
Nilai ASB |
8.646.918,59 |
| 2020 | 25.1.1.2.24 | Pemeliharaan Jalan Overlay Lebar 13,5 m | M1 | 8.646.918,59 | (belum diset) | |
55 |
NOMOR |
KATEGORI PEKERJAAN |
URAIAN KEGIATAN |
KOEF. |
SAT |
HARGA SATUAN |
HARGA |
26.1.1.1 |
Pembangunan Gedung Type A |
|
|
Titik |
|
|
24.1.1.4 |
- |
Pengukuran dan Pembuatan Bouwplank |
0.284 |
M1 |
113.758,40 |
32.307,39 |
24.1.2.1 |
- |
Penggalian Tanah Biasa sedalam s.d. 1 m untuk Konstruksi |
1.0318 |
M3 |
118.270,00 |
122.030,99 |
24.1.2.9 |
- |
Penimbunan kembali Tanah Galian |
0.3256 |
M3 |
85.740,00 |
27.916,94 |
24.1.2.11 |
- |
Penimbunan dengan Pasir urug |
0.1409 |
M3 |
471.628,02 |
66.452,39 |
24.1.3.12 |
- |
Pekerjaan Pemasangan Batu Kali (1 Pc : 4 Ps) |
0.3256 |
M3 |
1.390.242,02 |
452.662,80 |
24.1.3.23 |
- |
Pembuatan Lubang Strous Pile diameter 20 cm kedalaman 3 m |
0.0333 |
titik |
193.385,05 |
6.439,72 |
24.1.4.1 |
- |
Beton untuk Lantai Kerja |
0.0493 |
M3 |
568.825,93 |
28.043,12 |
24.1.4.3 |
- |
Beton mutu f'c 7,4 Mpa (K-100), slump (12±2) cm. w/c=0,87, dengan Molen |
0.0444 |
M3 |
1.689.836,57 |
75.028,74 |
24.1.4.23 |
- |
Beton mutu f'c 19,3 Mpa (K-225), slump (12±2) cm. w/c=0,58, dengan Molen |
0.0276 |
M3 |
1.943.652,28 |
53.644,80 |
24.1.4.57 |
- |
Pekerjaan Pondasi Beton Bertulang (150 kg besi + Bekisting) |
0.0528 |
M3 |
6.383.804,41 |
337.064,87 |
24.1.4.60 |
- |
Pekerjaan Sloof Beton Bertulang (200 kg besi + Bekisting) |
0.0222 |
M3 |
7.944.915,55 |
176.377,12 |
24.1.4.64 |
- |
Pekerjaan Balok Beton Bertulang (200 kg besi + Bekisting) |
0.0167 |
M3 |
10.149.718,50 |
169.500,29 |
24.1.4.65 |
- |
Pekerjaan Balok Beton Bertulang (150 kg besi + Bekisting) |
0.0238 |
M3 |
9.262.468,50 |
220.446,76 |
24.1.4.77 |
- |
Pekerjaan Kolom Praktis (11 x 11 cm) |
0.324 |
M1 |
134.625,10 |
43.618,53 |
24.1.6.7 |
- |
Dinding Batu Merah 1 Pc : 4 Pp tebal 1/2 bata |
3.0456 |
M2 |
155.098,30 |
472.367,38 |
24.1.6.8 |
- |
Dinding Batu Merah 1 Pc : 5 Pp tebal 1/2 bata |
0.113 |
M2 |
150.726,50 |
17.032,09 |
24.1.6.18 |
- |
Plesteran Halus 1 Pc : 4 Ps tebal 1.5 cm |
6.2042 |
M2 |
99.416,60 |
616.800,46 |
24.1.6.26 |
- |
Pasang Benangan 1 Pc: 2Ps |
0.74 |
M |
40.230,50 |
29.770,57 |
24.1.7.4 |
- |
Pengecatan Kayu (1 plamir, 1 lapis cat dasar, 3 lapis cat penutup) |
0.3921 |
M2 |
82.723,10 |
32.435,73 |
24.1.7.7 |
- |
Pengecatan Dinding Dalam Baru |
7.297 |
M2 |
45.835,85 |
334.464,20 |
24.1.7.12 |
- |
Pengecatan Dinding Luar Baru |
0.873 |
M2 |
57.917,56 |
50.562,03 |
24.1.8.2 |
- |
Pemasangan Lantai Keramik 20x20 cm |
0.1515 |
M2 |
486.460,50 |
73.698,77 |
24.1.8.8 |
- |
Pemasangan plint keramik ukuran 10cm x 20 cm |
0.1354 |
M1 |
57.412,30 |
7.773,63 |
24.1.8.16 |
- |
Dinding Keramik ukuran 20x25 cm |
0.1932 |
M2 |
584.363,80 |
112.899,09 |
24.1.8.19 |
- |
Pembuatan/Pemasangan Hardener Floor (Granit Trase Corak) |
0.9202 |
M2 |
75.971,20 |
69.908,70 |
24.1.9.13 |
- |
Pekerjaan Konstruksi Atap Kuda-Kuda/Gording Baja WF |
42.3708 |
kilogram |
44.850,60 |
1.900.355,77 |
24.1.9.17 |
- |
Pemasang rangka atap Galvalume 0.75 |
0.01 |
M2 |
81.466,00 |
814,66 |
24.1.9.26 |
- |
Pemasangan Penutup Atap Galvalume |
1.6243 |
M2 |
746.496,53 |
1.212.534,31 |
24.1.9.29 |
- |
Pemasangan Jurai Genteng Galvalume Tebal 4 mm (m) |
0.068 |
M1 |
1.159.312,51 |
78.833,26 |
24.1.9.31 |
- |
Pemasangan Listplank Kayu Kelas II |
0.0018 |
M1 |
215.764,84 |
388,38 |
24.1.9.57 |
- |
Pemasangan List plafond Gypsum Profil 4 " |
1.3536 |
M1 |
18.304,80 |
24.777,38 |
24.1.9.63 |
- |
Pemasangan Plafon Kalsiboard Rangka Aluminium |
1.2058 |
M2 |
906.665,19 |
1.093.256,94 |
24.1.10.10 |
- |
Daun Pintu Panil Kayu Kelas II |
0.1058 |
M2 |
1.348.926,99 |
142.716,48 |
24.1.10.15 |
- |
Pemasangan Kaca Mati Rayban tebal 5 mm |
0.0422 |
M2 |
384.815,45 |
16.239,21 |
24.1.10.20 |
- |
Pemasangan Kunci Tanam Besar 2x Putar kuningan |
0.076 |
buah |
187.054,00 |
14.216,10 |
24.1.10.23 |
- |
Pemasangan Engsel Kuningan Untuk Pintu |
0.152 |
stel |
124.695,44 |
18.953,71 |
24.1.10.29 |
- |
Pemasangan Hak Angin (Sikutan) |
0.48 |
stel |
64.714,00 |
31.062,72 |
24.1.10.40 |
- |
Pemasangan Daun Pintu PVC |
0.0286 |
buah |
4.879.270,01 |
139.547,12 |
24.1.11.1 |
- |
Pemasangan Titik Stop Kontak Gedung |
0.06 |
titik |
164.792,00 |
9.887,52 |
24.1.11.2 |
- |
Pemasangan Titik Lampu Gedung |
0.12 |
titik |
164.792,00 |
19.775,04 |
24.1.12.9 |
- |
Pemasangan Saluran Pipa diameter 1'' |
0.4644 |
meter |
31.098,24 |
14.442,02 |
24.1.12.13 |
- |
Pemasangan Saluran Pipa diameter 4'' |
0.4498 |
meter |
68.233,88 |
30.691,60 |
24.1.12.16 |
- |
Pemasangan Kran Air |
0.032 |
buah |
89.511,00 |
2.864,35 |
24.1.12.18 |
- |
Kloset Duduk Porselen |
0.0286 |
buah |
4.639.511,01 |
132.690,01 |
24.1.12.19 |
- |
Pemasangan Wastafel |
0.008 |
buah |
578.722,02 |
4.629,78 |
24.2.3.17 |
- |
Pasangan Batu tanpa Adukan (Aanstamping) |
0.1184 |
M3 |
624.945,01 |
73.993,49 |
|
|
|
|
|
Nilai ASB |
8.591.916,96 |
| 2020 | 26.1.1.1.1 | Pembangunan Gedung Type A | M2 | 8.591.916,96 | (belum diset) | |
56 |
NOMOR |
KATEGORI PEKERJAAN |
URAIAN KEGIATAN |
KOEF. |
SAT |
HARGA SATUAN |
HARGA |
25.1.1.2 |
Pemeliharaan Jalan Overlay Lebar 13 m |
|
|
Titik |
|
|
25.1.1.2.4 |
- |
Pemeliharaan Jalan Overlay |
13 |
M2 |
640.512,49 |
8.326.662,34 |
|
|
|
|
|
Nilai ASB |
8.326.662,34 |
| 2020 | 25.1.1.2.23 | Pemeliharaan Jalan Overlay Lebar 13 m | M1 | 8.326.662,34 | (belum diset) | |
57 |
NOMOR |
KATEGORI PEKERJAAN |
URAIAN KEGIATAN |
KOEF. |
SAT |
HARGA SATUAN |
HARGA |
26.1.1.2 |
Pembangunan Gedung Type B |
|
|
Titik |
|
|
24.1.1.4 |
- |
Pengukuran dan Pembuatan Bouwplank |
0.4167 |
M1 |
113.758,40 |
47.403,13 |
24.1.2.2 |
- |
Penggalian Tanah Biasa sedalam s.d. 2 m untuk Konstruksi |
1.221 |
M3 |
145.026,00 |
177.076,74 |
24.1.2.9 |
- |
Penimbunan kembali Tanah Galian |
0.407 |
M3 |
85.740,00 |
34.896,18 |
24.1.2.11 |
- |
Penimbunan dengan Pasir urug |
0.1638 |
M3 |
471.628,02 |
77.252,67 |
24.1.3.12 |
- |
Pekerjaan Pemasangan Batu Kali (1 Pc : 4 Ps) |
0.407 |
M3 |
1.390.242,02 |
565.828,51 |
24.1.3.23 |
- |
Pembuatan Lubang Strous Pile diameter 20 cm kedalaman 3 m |
0.0283 |
titik |
193.385,05 |
5.472,80 |
24.1.4.1 |
- |
Beton untuk Lantai Kerja |
0.0455 |
M3 |
568.825,93 |
25.881,58 |
24.1.4.3 |
- |
Beton mutu f'c 7,4 Mpa (K-100), slump (12±2) cm. w/c=0,87, dengan Molen |
0.0555 |
M3 |
1.689.836,57 |
93.785,93 |
24.1.4.57 |
- |
Pekerjaan Pondasi Beton Bertulang (150 kg besi + Bekisting) |
0.09 |
M3 |
6.383.804,41 |
574.542,42 |
24.1.4.61 |
- |
Pekerjaan Sloof Beton Bertulang (150 kg besi + Bekisting) |
0.0278 |
M3 |
7.057.665,55 |
196.203,10 |
24.1.4.64 |
- |
Pekerjaan Balok Beton Bertulang (200 kg besi + Bekisting) |
0.0208 |
M3 |
10.149.718,50 |
211.114,15 |
24.1.4.65 |
- |
Pekerjaan Balok Beton Bertulang (150 kg besi + Bekisting) |
0.036 |
M3 |
9.262.468,50 |
333.448,85 |
24.1.4.77 |
- |
Pekerjaan Kolom Praktis (11 x 11 cm) |
0.2625 |
M1 |
134.625,10 |
35.339,09 |
24.1.6.7 |
- |
Dinding Batu Merah 1 Pc : 4 Pp tebal 1/2 bata |
3.5063 |
M2 |
155.098,30 |
543.821,17 |
24.1.6.18 |
- |
Plesteran Halus 1 Pc : 4 Ps tebal 1.5 cm |
7.1425 |
M2 |
99.416,60 |
710.083,07 |
24.1.6.26 |
- |
Pasang Benangan 1 Pc: 2Ps |
0.925 |
M |
40.230,50 |
37.213,21 |
24.1.7.4 |
- |
Pengecatan Kayu (1 plamir, 1 lapis cat dasar, 3 lapis cat penutup) |
0.4875 |
M2 |
82.723,10 |
40.327,51 |
24.1.7.7 |
- |
Pengecatan Dinding Dalam Baru |
8.2375 |
M2 |
45.835,85 |
377.572,83 |
24.1.7.12 |
- |
Pengecatan Dinding Luar Baru |
1.1438 |
M2 |
57.917,56 |
66.246,11 |
24.1.8.2 |
- |
Pemasangan Lantai Keramik 20x20 cm |
0.1413 |
M2 |
486.460,50 |
68.736,86 |
24.1.8.5 |
- |
Pemasangan Lantai Keramik ukuran 40x40 cm |
0.8192 |
M2 |
1.423.510,50 |
1.166.139,77 |
24.1.8.8 |
- |
Pemasangan plint keramik ukuran 10cm x 20 cm |
0.1558 |
M1 |
57.412,30 |
8.944,84 |
24.1.8.16 |
- |
Dinding Keramik ukuran 20x25 cm |
0.29 |
M2 |
584.363,80 |
169.465,50 |
24.1.9.12 |
- |
Pemasangan Polycarbonat |
0.02 |
M2 |
265.208,80 |
5.304,18 |
24.1.9.17 |
- |
Pemasang rangka atap Galvalume 0.75 |
0.8239 |
M2 |
81.466,00 |
67.119,84 |
24.1.9.26 |
- |
Pemasangan Penutup Atap Galvalume |
0.8039 |
M2 |
746.496,53 |
600.108,56 |
24.1.9.29 |
- |
Pemasangan Jurai Genteng Galvalume Tebal 4 mm (m) |
0.0958 |
M1 |
1.159.312,51 |
111.062,14 |
24.1.9.31 |
- |
Pemasangan Listplank Kayu Kelas II |
0.0026 |
M1 |
215.764,84 |
560,99 |
24.1.9.57 |
- |
Pemasangan List plafond Gypsum Profil 4 " |
1.5583 |
M1 |
18.304,80 |
28.524,37 |
24.1.9.64 |
- |
Pemasangan Plafond Kalsiboard Rangka Plafon Metal Furing |
1.225 |
M2 |
961.757,19 |
1.178.152,59 |
24.1.10.10 |
- |
Daun Pintu Panil Kayu Kelas II |
0.1418 |
M2 |
1.348.926,99 |
191.277,85 |
24.1.10.14 |
- |
Pemasangan Kaca Mati tebal 5 mm |
0.0587 |
M2 |
326.075,45 |
19.140,63 |
24.1.10.20 |
- |
Pemasangan Kunci Tanam Besar 2x Putar kuningan |
0.1 |
buah |
187.054,00 |
18.705,40 |
24.1.10.23 |
- |
Pemasangan Engsel Kuningan Untuk Pintu |
0.2 |
stel |
124.695,44 |
24.939,09 |
24.1.10.29 |
- |
Pemasangan Hak Angin (Sikutan) |
0.0667 |
stel |
64.714,00 |
4.316,42 |
24.1.10.41 |
- |
Pemasangan Kusen Alumunium Profil 4" Putih |
0.7863 |
M1 |
399.836,84 |
314.391,71 |
24.1.11.1 |
- |
Pemasangan Titik Stop Kontak Gedung |
0.0833 |
titik |
164.792,00 |
13.727,17 |
24.1.11.2 |
- |
Pemasangan Titik Lampu Gedung |
0.1417 |
titik |
164.792,00 |
23.351,03 |
24.2.3.17 |
- |
Pasangan Batu tanpa Adukan (Aanstamping) |
0.148 |
M3 |
624.945,01 |
92.491,86 |
|
|
|
|
|
Nilai ASB |
8.259.969,82 |
| 2020 | 26.1.1.2.1 | Pembangunan Gedung Type B | M2 | 8.259.969,82 | (belum diset) | |
58 |
NOMOR |
KATEGORI PEKERJAAN |
URAIAN KEGIATAN |
KOEF. |
SAT |
HARGA SATUAN |
HARGA |
27.1.1.146 |
Pemasangan Lampu HPS 150 W - 1 Phase - Tiang Tanam Oktagonal |
|
|
Titik |
|
|
24.2.2.1 |
- |
Pemasangan Konektor Kabel |
2 |
buah |
1.661,45 |
3.322,90 |
24.2.2.14 |
- |
Pemasangan / Penarikan Kabel NFA2X (Twisted) 4 x 16 mm |
50 |
M |
32.059,81 |
1.602.990,50 |
24.2.2.28 |
- |
Perakitan dan Pemasangan Panel Lampu PJU - 1 Phase 2200VA |
0.1 |
unit |
1.636.566,95 |
163.656,70 |
24.2.2.40 |
- |
Pemasangan Panel Meter 1 Phase |
0.1 |
unit |
288.360,00 |
28.836,00 |
24.2.2.43 |
- |
Pemasangan Lampu HPS 150 W/220 V Lengkap Armateur, Balast, Ignitor & Capasitor |
1 |
unit |
2.642.075,00 |
2.642.075,00 |
24.2.2.51 |
- |
Pemasangan Tiang Oktagonal 5 m Single Hot Dipped Galvanized dengan Flenders |
1 |
unit |
3.655.059,00 |
3.655.059,00 |
117.1.3.8.1.47 |
- |
Kabel NYM 3 x 2,5 mm |
0.14 |
Roll |
858.100,00 |
120.134,00 |
|
|
|
|
|
Nilai ASB |
8.216.074,10 |
| 2020 | 27.1.1.146.1 | Pemasangan Lampu HPS 150 W - 1 Phase - Tiang Tanam Oktagonal | titik | 8.216.074,10 | (belum diset) | |
59 |
NOMOR |
KATEGORI PEKERJAAN |
URAIAN KEGIATAN |
KOEF. |
SAT |
HARGA SATUAN |
HARGA |
25.1.2.1 |
Pembangunan Rumah Kompos Landasan Rigid |
|
|
Titik |
|
|
24.1.1.4 |
- |
Pengukuran dan Pembuatan Bouwplank |
0.1 |
M1 |
113.758,40 |
11.375,84 |
24.1.2.5 |
- |
Penggalian Tanah Lumpur |
0.367 |
M3 |
190.266,01 |
69.827,63 |
24.1.2.22 |
- |
Penimbunan dengan Sirtu |
0.9 |
M3 |
281.590,28 |
253.431,25 |
24.1.3.12 |
- |
Pekerjaan Pemasangan Batu Kali (1 Pc : 4 Ps) |
0.061 |
M3 |
1.390.242,02 |
84.804,76 |
24.1.3.24 |
- |
Pembuatan Lubang Strous Pile diameter 30 cm kedalaman 3 m |
0.267 |
titik |
232.058,65 |
61.959,66 |
24.1.4.23 |
- |
Beton mutu f'c 19,3 Mpa (K-225), slump (12±2) cm. w/c=0,58, dengan Molen |
0.001 |
M3 |
1.943.652,28 |
1.943,65 |
24.1.4.43 |
- |
Beton mutu f'c 31,2 Mpa (K-350), slump (12±2) cm. w/c=0,48, dengan Molen |
0.18 |
M3 |
2.201.588,97 |
396.286,03 |
24.1.4.47 |
- |
Tulangan Beton dengan besi ulir |
3.7798 |
kilogram |
23.886,93 |
90.287,81 |
24.1.4.60 |
- |
Pekerjaan Sloof Beton Bertulang (200 kg besi + Bekisting) |
0.1035 |
M3 |
7.944.915,55 |
822.298,77 |
24.1.4.64 |
- |
Pekerjaan Balok Beton Bertulang (200 kg besi + Bekisting) |
0.0012 |
M3 |
10.149.718,50 |
12.179,66 |
24.1.4.65 |
- |
Pekerjaan Balok Beton Bertulang (150 kg besi + Bekisting) |
0.033 |
M3 |
9.262.468,50 |
305.661,46 |
24.1.6.2 |
- |
Dinding Batu Merah 1 Pc : 3 Pp tebal 1 bata |
0.298 |
M2 |
336.967,11 |
100.416,20 |
24.1.6.16 |
- |
Plesteran Halus 1 Pc : 2 Ps tebal 1.5 cm |
2.99 |
M2 |
108.694,40 |
324.996,26 |
24.1.6.25 |
- |
Pemasangan acian |
2.99 |
M2 |
60.790,00 |
181.762,10 |
24.1.6.26 |
- |
Pasang Benangan 1 Pc: 2Ps |
10.5599 |
M |
40.230,50 |
424.830,06 |
24.1.7.4 |
- |
Pengecatan Kayu (1 plamir, 1 lapis cat dasar, 3 lapis cat penutup) |
6.114 |
M2 |
82.723,10 |
505.769,02 |
24.1.7.10 |
- |
Pengecatan Dasar Meni Besi |
0.039 |
M2 |
50.512,00 |
1.969,97 |
24.1.8.2 |
- |
Pemasangan Lantai Keramik 20x20 cm |
0.061 |
M2 |
486.460,50 |
29.674,09 |
24.1.8.16 |
- |
Dinding Keramik ukuran 20x25 cm |
0.122 |
M2 |
584.363,80 |
71.292,38 |
24.1.9.2 |
- |
Pemasangan Konstruksi Kuda-Kuda Konvensional Kayu Kelas II bentang 6 m. |
0.027 |
M3 |
19.216.990,36 |
518.858,75 |
24.1.9.4 |
- |
Pemasangan konstruksi gordeng kayu kelas II |
0.023 |
M3 |
21.218.480,39 |
488.025,05 |
24.1.9.15 |
- |
Pemasangan Reng /Usuk Kayu Kelas II |
5.317 |
M2 |
452.785,41 |
2.407.460,00 |
24.1.9.22 |
- |
Pemasangan Atap Sirap Asbes Tebal 4 mm |
0.16 |
M2 |
609.752,40 |
97.560,38 |
24.1.9.29 |
- |
Pemasangan Jurai Genteng Galvalume Tebal 4 mm (m) |
0.25 |
M1 |
1.159.312,51 |
289.828,13 |
24.1.9.31 |
- |
Pemasangan Listplank Kayu Kelas II |
1.933 |
M1 |
215.764,84 |
417.073,44 |
24.1.9.55 |
- |
Pemasangan Plafon Gypsum Board (120x240) 9 mm |
0.067 |
M2 |
62.325,80 |
4.175,83 |
24.1.9.57 |
- |
Pemasangan List plafond Gypsum Profil 4 " |
0.133 |
M1 |
18.304,80 |
2.434,54 |
24.1.10.14 |
- |
Pemasangan Kaca Mati tebal 5 mm |
0.002 |
M2 |
326.075,45 |
652,15 |
24.1.10.19 |
- |
Pemasangan Kunci Tanam Kecil |
0.017 |
buah |
160.354,00 |
2.726,02 |
24.1.10.23 |
- |
Pemasangan Engsel Kuningan Untuk Pintu |
0.05 |
stel |
124.695,44 |
6.234,77 |
24.1.10.40 |
- |
Pemasangan Daun Pintu PVC |
0.021 |
buah |
4.879.270,01 |
102.464,67 |
24.1.11.1 |
- |
Pemasangan Titik Stop Kontak Gedung |
0.017 |
titik |
164.792,00 |
2.801,46 |
24.1.11.2 |
- |
Pemasangan Titik Lampu Gedung |
0.067 |
titik |
164.792,00 |
11.041,06 |
24.1.12.3 |
- |
Pemasangan Dasar Saluran R.25 Segmen |
0.058 |
meter |
96.386,56 |
5.590,42 |
24.1.12.8 |
- |
Pemasangan Saluran Pipa diameter ¾'' |
0.067 |
meter |
29.478,24 |
1.975,04 |
24.1.12.13 |
- |
Pemasangan Saluran Pipa diameter 4'' |
0.084 |
meter |
68.233,88 |
5.731,65 |
24.1.12.16 |
- |
Pemasangan Kran Air |
0.033 |
buah |
89.511,00 |
2.953,86 |
24.1.14.5 |
- |
Pekerjaan Besi Pipa Galvanis 2 " (Medium) |
0.133 |
meter |
59.416,00 |
7.902,33 |
|
|
|
|
|
Nilai ASB |
8.126.256,18 |
| 2020 | 25.1.2.1.8 | Pembangunan Rumah Kompos Landasan Rigid | M2 | 8.126.256,18 | (belum diset) | |
60 |
NOMOR |
KATEGORI PEKERJAAN |
URAIAN KEGIATAN |
KOEF. |
SAT |
HARGA SATUAN |
HARGA |
25.1.1.2 |
Pemeliharaan Jalan Overlay Lebar 12,5 m |
|
|
Titik |
|
|
25.1.1.2.4 |
- |
Pemeliharaan Jalan Overlay |
12.5 |
M2 |
640.512,49 |
8.006.406,10 |
|
|
|
|
|
Nilai ASB |
8.006.406,10 |
| 2020 | 25.1.1.2.22 | Pemeliharaan Jalan Overlay Lebar 12,5 m | M1 | 8.006.406,10 | (belum diset) | |