1401 |
NOMOR |
URAIAN KEGIATAN |
KOEF. |
SAT |
HARGA SATUAN |
HARGA |
24.1.10.69 |
Pemasangan Kusen Metal Type V 4 |
|
unit |
|
|
|
Upah: |
|
|
|
|
123.1.1.1.1.5 |
Kepala Tukang |
0.0168 |
OH |
236.200,00 |
3.968,16 |
123.1.1.1.1.6 |
Mandor |
0.0028 |
OH |
206.800,00 |
579,04 |
123.1.1.1.1.14 |
Pekerja Terlatih |
0.672 |
OH |
150.800,00 |
101.337,60 |
123.1.1.1.1.23 |
Tukang |
0.336 |
OH |
177.500,00 |
59.640,00 |
|
|
|
|
Jumlah |
165.524,80 |
|
Bahan/Material: |
|
|
|
|
117.1.1.1.22.406 |
Kusen Metal type V 4 |
1 |
unit |
637.700,00 |
637.700,00 |
|
|
|
|
Jumlah |
637.700,00 |
|
Sewa Peralatan: |
|
|
|
|
|
|
|
|
Jumlah |
0,00 |
|
|
|
|
Nilai HSPK |
803.224,80 |
| 2020 | 24.1.10.69 | Pemasangan Kusen Metal Type V 4 | unit | 803.224,80 | Tidak Dipakai | |
1402 |
NOMOR |
URAIAN KEGIATAN |
KOEF. |
SAT |
HARGA SATUAN |
HARGA |
24.1.10.70 |
Pemasangan Kusen Metal Type V 4 K |
|
unit |
|
|
|
Upah: |
|
|
|
|
123.1.1.1.1.5 |
Kepala Tukang |
0.0114 |
OH |
236.200,00 |
2.692,68 |
123.1.1.1.1.6 |
Mandor |
0.0019 |
OH |
206.800,00 |
392,92 |
123.1.1.1.1.14 |
Pekerja Terlatih |
0.456 |
OH |
150.800,00 |
68.764,80 |
123.1.1.1.1.23 |
Tukang |
0.228 |
OH |
177.500,00 |
40.470,00 |
|
|
|
|
Jumlah |
112.320,40 |
|
Bahan/Material: |
|
|
|
|
117.1.1.1.22.407 |
Kusen Metal type V 4 K |
1 |
unit |
600.300,00 |
600.300,00 |
|
|
|
|
Jumlah |
600.300,00 |
|
Sewa Peralatan: |
|
|
|
|
|
|
|
|
Jumlah |
0,00 |
|
|
|
|
Nilai HSPK |
712.620,40 |
| 2020 | 24.1.10.70 | Pemasangan Kusen Metal Type V 4 K | unit | 712.620,40 | Tidak Dipakai | |
1403 |
NOMOR |
URAIAN KEGIATAN |
KOEF. |
SAT |
HARGA SATUAN |
HARGA |
24.1.10.71 |
Pemasangan Kusen Metal Jendela Tipe 1 |
|
unit |
|
|
|
Upah: |
|
|
|
|
123.1.1.1.1.5 |
Kepala Tukang |
0.0558 |
OH |
236.200,00 |
13.179,96 |
123.1.1.1.1.6 |
Mandor |
0.0093 |
OH |
206.800,00 |
1.923,24 |
123.1.1.1.1.14 |
Pekerja Terlatih |
2.232 |
OH |
150.800,00 |
336.585,62 |
123.1.1.1.1.23 |
Tukang |
1.116 |
OH |
177.500,00 |
198.090,01 |
|
|
|
|
Jumlah |
549.778,83 |
|
Bahan/Material: |
|
|
|
|
117.1.1.1.22.370 |
Kusen Metal Jendela Tipe 1 |
1 |
unit |
2.242.500,00 |
2.242.500,00 |
|
|
|
|
Jumlah |
2.242.500,00 |
|
Sewa Peralatan: |
|
|
|
|
|
|
|
|
Jumlah |
0,00 |
|
|
|
|
Nilai HSPK |
2.792.278,83 |
| 2020 | 24.1.10.71 | Pemasangan Kusen Metal Jendela Tipe 1 | unit | 2.792.278,83 | Tidak Dipakai | |
1404 |
NOMOR |
URAIAN KEGIATAN |
KOEF. |
SAT |
HARGA SATUAN |
HARGA |
24.1.10.72 |
Pemasangan Kusen Metal Jendela Tipe 2 |
|
unit |
|
|
|
Upah: |
|
|
|
|
123.1.1.1.1.5 |
Kepala Tukang |
0.0414 |
OH |
236.200,00 |
9.778,68 |
123.1.1.1.1.6 |
Mandor |
0.0069 |
OH |
206.800,00 |
1.426,92 |
123.1.1.1.1.14 |
Pekerja Terlatih |
1.656 |
OH |
150.800,00 |
249.724,80 |
123.1.1.1.1.23 |
Tukang |
0.828 |
OH |
177.500,00 |
146.970,00 |
|
|
|
|
Jumlah |
407.900,40 |
|
Bahan/Material: |
|
|
|
|
117.1.1.1.22.371 |
Kusen Metal Jendela Tipe 2 |
1 |
unit |
1.670.200,00 |
1.670.200,00 |
|
|
|
|
Jumlah |
1.670.200,00 |
|
Sewa Peralatan: |
|
|
|
|
|
|
|
|
Jumlah |
0,00 |
|
|
|
|
Nilai HSPK |
2.078.100,40 |
| 2020 | 24.1.10.72 | Pemasangan Kusen Metal Jendela Tipe 2 | unit | 2.078.100,40 | Tidak Dipakai | |
1405 |
NOMOR |
URAIAN KEGIATAN |
KOEF. |
SAT |
HARGA SATUAN |
HARGA |
24.1.10.73 |
Pemasangan Kusen Metal Jendela Tipe 3 |
|
unit |
|
|
|
Upah: |
|
|
|
|
123.1.1.1.1.5 |
Kepala Tukang |
0.0288 |
OH |
236.200,00 |
6.802,56 |
123.1.1.1.1.6 |
Mandor |
0.0048 |
OH |
206.800,00 |
992,64 |
123.1.1.1.1.14 |
Pekerja Terlatih |
1.152 |
OH |
150.800,00 |
173.721,59 |
123.1.1.1.1.23 |
Tukang |
0.576 |
OH |
177.500,00 |
102.240,00 |
|
|
|
|
Jumlah |
283.756,79 |
|
Bahan/Material: |
|
|
|
|
117.1.1.1.22.372 |
Kusen Metal Jendela Tipe 3 |
1 |
unit |
1.168.600,00 |
1.168.600,00 |
|
|
|
|
Jumlah |
1.168.600,00 |
|
Sewa Peralatan: |
|
|
|
|
|
|
|
|
Jumlah |
0,00 |
|
|
|
|
Nilai HSPK |
1.452.356,79 |
| 2020 | 24.1.10.73 | Pemasangan Kusen Metal Jendela Tipe 3 | unit | 1.452.356,79 | Tidak Dipakai | |
1406 |
NOMOR |
URAIAN KEGIATAN |
KOEF. |
SAT |
HARGA SATUAN |
HARGA |
24.1.10.74 |
Pemasangan Kusen Metal Jendela Tipe 4 |
|
unit |
|
|
|
Upah: |
|
|
|
|
123.1.1.1.1.5 |
Kepala Tukang |
0.0162 |
OH |
236.200,00 |
3.826,44 |
123.1.1.1.1.6 |
Mandor |
0.0027 |
OH |
206.800,00 |
558,36 |
123.1.1.1.1.14 |
Pekerja Terlatih |
0.648 |
OH |
150.800,00 |
97.718,40 |
123.1.1.1.1.23 |
Tukang |
0.324 |
OH |
177.500,00 |
57.510,00 |
|
|
|
|
Jumlah |
159.613,20 |
|
Bahan/Material: |
|
|
|
|
117.1.1.1.22.373 |
Kusen Jendela Metal Tipe 4 |
1 |
unit |
644.400,00 |
644.400,00 |
|
|
|
|
Jumlah |
644.400,00 |
|
Sewa Peralatan: |
|
|
|
|
|
|
|
|
Jumlah |
0,00 |
|
|
|
|
Nilai HSPK |
804.013,20 |
| 2020 | 24.1.10.74 | Pemasangan Kusen Metal Jendela Tipe 4 | unit | 804.013,20 | Tidak Dipakai | |
1407 |
NOMOR |
URAIAN KEGIATAN |
KOEF. |
SAT |
HARGA SATUAN |
HARGA |
24.1.10.75 |
Pemasangan Kusen Metal Jendela Tipe 5 |
|
unit |
|
|
|
Upah: |
|
|
|
|
123.1.1.1.1.5 |
Kepala Tukang |
0.0222 |
OH |
236.200,00 |
5.243,64 |
123.1.1.1.1.6 |
Mandor |
0.0037 |
OH |
206.800,00 |
765,16 |
123.1.1.1.1.14 |
Pekerja Terlatih |
0.888 |
OH |
150.800,00 |
133.910,40 |
123.1.1.1.1.23 |
Tukang |
0.444 |
OH |
177.500,00 |
78.810,00 |
|
|
|
|
Jumlah |
218.729,20 |
|
Bahan/Material: |
|
|
|
|
117.1.1.1.22.374 |
Kusen Metal Jendela Tipe 5 |
1 |
unit |
899.200,00 |
899.200,00 |
|
|
|
|
Jumlah |
899.200,00 |
|
Sewa Peralatan: |
|
|
|
|
|
|
|
|
Jumlah |
0,00 |
|
|
|
|
Nilai HSPK |
1.117.929,20 |
| 2020 | 24.1.10.75 | Pemasangan Kusen Metal Jendela Tipe 5 | unit | 1.117.929,20 | Tidak Dipakai | |
1408 |
NOMOR |
URAIAN KEGIATAN |
KOEF. |
SAT |
HARGA SATUAN |
HARGA |
24.1.10.76 |
Pemasangan Kusen Metal Jendela Tipe 6 |
|
unit |
|
|
|
Upah: |
|
|
|
|
123.1.1.1.1.5 |
Kepala Tukang |
0.018 |
OH |
236.200,00 |
4.251,60 |
123.1.1.1.1.6 |
Mandor |
0.003 |
OH |
206.800,00 |
620,40 |
123.1.1.1.1.14 |
Pekerja Terlatih |
0.72 |
OH |
150.800,00 |
108.576,00 |
123.1.1.1.1.23 |
Tukang |
0.36 |
OH |
177.500,00 |
63.900,00 |
|
|
|
|
Jumlah |
177.348,01 |
|
Bahan/Material: |
|
|
|
|
117.1.1.1.22.375 |
Kusen Metal Jendela Tipe 6 |
1 |
unit |
716.400,00 |
716.400,00 |
|
|
|
|
Jumlah |
716.400,00 |
|
Sewa Peralatan: |
|
|
|
|
|
|
|
|
Jumlah |
0,00 |
|
|
|
|
Nilai HSPK |
893.748,01 |
| 2020 | 24.1.10.76 | Pemasangan Kusen Metal Jendela Tipe 6 | unit | 893.748,01 | Tidak Dipakai | |
1409 |
NOMOR |
URAIAN KEGIATAN |
KOEF. |
SAT |
HARGA SATUAN |
HARGA |
24.1.10.77 |
Pemasangan Kusen Metal Jendela Tipe 7 |
|
unit |
|
|
|
Upah: |
|
|
|
|
123.1.1.1.1.5 |
Kepala Tukang |
0.0132 |
OH |
236.200,00 |
3.117,84 |
123.1.1.1.1.6 |
Mandor |
0.0022 |
OH |
206.800,00 |
454,96 |
123.1.1.1.1.14 |
Pekerja Terlatih |
0.528 |
OH |
150.800,00 |
79.622,40 |
123.1.1.1.1.23 |
Tukang |
0.264 |
OH |
177.500,00 |
46.860,00 |
|
|
|
|
Jumlah |
130.055,20 |
|
Bahan/Material: |
|
|
|
|
117.1.1.1.22.376 |
Kusen Metal Jendela Tipe 7 |
1 |
unit |
540.300,00 |
540.300,00 |
|
|
|
|
Jumlah |
540.300,00 |
|
Sewa Peralatan: |
|
|
|
|
|
|
|
|
Jumlah |
0,00 |
|
|
|
|
Nilai HSPK |
670.355,20 |
| 2020 | 24.1.10.77 | Pemasangan Kusen Metal Jendela Tipe 7 | unit | 670.355,20 | Tidak Dipakai | |
1410 |
NOMOR |
URAIAN KEGIATAN |
KOEF. |
SAT |
HARGA SATUAN |
HARGA |
24.1.10.78 |
Pemasangan Kusen Metal Jendela Tipe 8 |
|
unit |
|
|
|
Upah: |
|
|
|
|
123.1.1.1.1.5 |
Kepala Tukang |
0.009 |
OH |
236.200,00 |
2.125,80 |
123.1.1.1.1.6 |
Mandor |
0.0015 |
OH |
206.800,00 |
310,20 |
123.1.1.1.1.14 |
Pekerja Terlatih |
0.36 |
OH |
150.800,00 |
54.288,00 |
123.1.1.1.1.23 |
Tukang |
0.18 |
OH |
177.500,00 |
31.950,00 |
|
|
|
|
Jumlah |
88.674,00 |
|
Bahan/Material: |
|
|
|
|
117.1.1.1.22.377 |
Kusen metal Jendela Tipe 8 |
1 |
unit |
356.900,00 |
356.900,00 |
|
|
|
|
Jumlah |
356.900,00 |
|
Sewa Peralatan: |
|
|
|
|
|
|
|
|
Jumlah |
0,00 |
|
|
|
|
Nilai HSPK |
445.574,00 |
| 2020 | 24.1.10.78 | Pemasangan Kusen Metal Jendela Tipe 8 | unit | 445.574,00 | Tidak Dipakai | |
1411 |
NOMOR |
URAIAN KEGIATAN |
KOEF. |
SAT |
HARGA SATUAN |
HARGA |
24.1.10.79 |
Pemasangan Kusen Metal Pintu Tipe 1 |
|
unit |
|
|
|
Upah: |
|
|
|
|
123.1.1.1.1.5 |
Kepala Tukang |
0.0312 |
OH |
236.200,00 |
7.369,44 |
123.1.1.1.1.6 |
Mandor |
0.0052 |
OH |
206.800,00 |
1.075,36 |
123.1.1.1.1.14 |
Pekerja Terlatih |
1.248 |
OH |
150.800,00 |
188.198,40 |
123.1.1.1.1.23 |
Tukang |
0.624 |
OH |
177.500,00 |
110.760,00 |
|
|
|
|
Jumlah |
307.403,21 |
|
Bahan/Material: |
|
|
|
|
117.1.1.1.22.378 |
Kusen Metal Pintu Tipe 1 |
1 |
unit |
1.256.700,00 |
1.256.700,00 |
|
|
|
|
Jumlah |
1.256.700,00 |
|
Sewa Peralatan: |
|
|
|
|
|
|
|
|
Jumlah |
0,00 |
|
|
|
|
Nilai HSPK |
1.564.103,21 |
| 2020 | 24.1.10.79 | Pemasangan Kusen Metal Pintu Tipe 1 | unit | 1.564.103,21 | Tidak Dipakai | |
1412 |
NOMOR |
URAIAN KEGIATAN |
KOEF. |
SAT |
HARGA SATUAN |
HARGA |
24.1.10.80 |
Pemasangan Kusen Metal Pintu Tipe 2 |
|
unit |
|
|
|
Upah: |
|
|
|
|
123.1.1.1.1.5 |
Kepala Tukang |
0.021 |
OH |
236.200,00 |
4.960,20 |
123.1.1.1.1.6 |
Mandor |
0.0035 |
OH |
206.800,00 |
723,80 |
123.1.1.1.1.14 |
Pekerja Terlatih |
0.84 |
OH |
150.800,00 |
126.672,00 |
123.1.1.1.1.23 |
Tukang |
0.42 |
OH |
177.500,00 |
74.550,00 |
|
|
|
|
Jumlah |
206.905,99 |
|
Bahan/Material: |
|
|
|
|
117.1.1.1.22.379 |
Kusen Metal Pintu Tipe 2 |
1 |
unit |
843.100,00 |
843.100,00 |
|
|
|
|
Jumlah |
843.100,00 |
|
Sewa Peralatan: |
|
|
|
|
|
|
|
|
Jumlah |
0,00 |
|
|
|
|
Nilai HSPK |
1.050.005,99 |
| 2020 | 24.1.10.80 | Pemasangan Kusen Metal Pintu Tipe 2 | unit | 1.050.005,99 | Tidak Dipakai | |
1413 |
NOMOR |
URAIAN KEGIATAN |
KOEF. |
SAT |
HARGA SATUAN |
HARGA |
24.1.10.81 |
Pemasangan Kusen Metal Pintu Tipe 3 |
|
unit |
|
|
|
Upah: |
|
|
|
|
123.1.1.1.1.5 |
Kepala Tukang |
0.0198 |
OH |
236.200,00 |
4.676,76 |
123.1.1.1.1.6 |
Mandor |
0.0033 |
OH |
206.800,00 |
682,44 |
123.1.1.1.1.14 |
Pekerja Terlatih |
0.792 |
OH |
150.800,00 |
119.433,60 |
123.1.1.1.1.23 |
Tukang |
0.396 |
OH |
177.500,00 |
70.290,00 |
|
|
|
|
Jumlah |
195.082,80 |
|
Bahan/Material: |
|
|
|
|
117.1.1.1.22.380 |
Kusen Metal Pintu Tipe 3 |
1 |
unit |
811.100,00 |
811.100,00 |
|
|
|
|
Jumlah |
811.100,00 |
|
Sewa Peralatan: |
|
|
|
|
|
|
|
|
Jumlah |
0,00 |
|
|
|
|
Nilai HSPK |
1.006.182,80 |
| 2020 | 24.1.10.81 | Pemasangan Kusen Metal Pintu Tipe 3 | unit | 1.006.182,80 | Tidak Dipakai | |
1414 |
NOMOR |
URAIAN KEGIATAN |
KOEF. |
SAT |
HARGA SATUAN |
HARGA |
24.1.10.82 |
Pemasangan Kusen Metal Pintu Tipe 4 |
|
unit |
|
|
|
Upah: |
|
|
|
|
123.1.1.1.1.5 |
Kepala Tukang |
0.018 |
OH |
236.200,00 |
4.251,60 |
123.1.1.1.1.6 |
Mandor |
0.003 |
OH |
206.800,00 |
620,40 |
123.1.1.1.1.14 |
Pekerja Terlatih |
0.72 |
OH |
150.800,00 |
108.576,00 |
123.1.1.1.1.23 |
Tukang |
0.36 |
OH |
177.500,00 |
63.900,00 |
|
|
|
|
Jumlah |
177.348,01 |
|
Bahan/Material: |
|
|
|
|
117.1.1.1.22.381 |
Kusen Metal Pintu Tipe 4 |
1 |
unit |
716.400,00 |
716.400,00 |
|
|
|
|
Jumlah |
716.400,00 |
|
Sewa Peralatan: |
|
|
|
|
|
|
|
|
Jumlah |
0,00 |
|
|
|
|
Nilai HSPK |
893.748,01 |
| 2020 | 24.1.10.82 | Pemasangan Kusen Metal Pintu Tipe 4 | unit | 893.748,01 | Tidak Dipakai | |
1415 |
NOMOR |
URAIAN KEGIATAN |
KOEF. |
SAT |
HARGA SATUAN |
HARGA |
24.1.10.83 |
Pemasangan Kusen Metal Pintu&Jendela |
|
unit |
|
|
|
Upah: |
|
|
|
|
123.1.1.1.1.5 |
Kepala Tukang |
0.0624 |
OH |
236.200,00 |
14.738,88 |
123.1.1.1.1.6 |
Mandor |
0.0104 |
OH |
206.800,00 |
2.150,72 |
123.1.1.1.1.14 |
Pekerja Terlatih |
2.496 |
OH |
150.800,00 |
376.396,81 |
123.1.1.1.1.23 |
Tukang |
1.248 |
OH |
177.500,00 |
221.520,00 |
|
|
|
|
Jumlah |
614.806,41 |
|
Bahan/Material: |
|
|
|
|
117.1.1.1.22.382 |
Kusen Metal Pintu & Jendela |
1 |
unit |
2.513.300,00 |
2.513.300,00 |
|
|
|
|
Jumlah |
2.513.300,00 |
|
Sewa Peralatan: |
|
|
|
|
|
|
|
|
Jumlah |
0,00 |
|
|
|
|
Nilai HSPK |
3.128.106,41 |
| 2020 | 24.1.10.83 | Pemasangan Kusen Metal Pintu&Jendela | unit | 3.128.106,41 | Tidak Dipakai | |
1416 |
NOMOR |
URAIAN KEGIATAN |
KOEF. |
SAT |
HARGA SATUAN |
HARGA |
24.1.10.84 |
Pemasangan Kusen Aluminium Type J 1 |
|
unit |
|
|
|
Upah: |
|
|
|
|
123.1.1.1.1.5 |
Kepala Tukang |
0.102 |
OH |
236.200,00 |
24.092,40 |
123.1.1.1.1.6 |
Mandor |
0.017 |
OH |
206.800,00 |
3.515,60 |
123.1.1.1.1.14 |
Pekerja Terlatih |
4.08 |
OH |
150.800,00 |
615.263,99 |
123.1.1.1.1.23 |
Tukang |
2.04 |
OH |
177.500,00 |
362.099,99 |
|
|
|
|
Jumlah |
1.004.971,98 |
|
Bahan/Material: |
|
|
|
|
117.1.1.1.22.345 |
Kusen Aluminium Tipe J 1 |
1 |
unit |
3.732.600,00 |
3.732.600,00 |
|
|
|
|
Jumlah |
3.732.600,00 |
|
Sewa Peralatan: |
|
|
|
|
|
|
|
|
Jumlah |
0,00 |
|
|
|
|
Nilai HSPK |
4.737.571,98 |
| 2020 | 24.1.10.84 | Pemasangan Kusen Aluminium Type J 1 | unit | 4.737.571,98 | Tidak Dipakai | |
1417 |
NOMOR |
URAIAN KEGIATAN |
KOEF. |
SAT |
HARGA SATUAN |
HARGA |
24.1.10.85 |
Pemasangan Kusen Aluminium Type J 1 K |
|
unit |
|
|
|
Upah: |
|
|
|
|
123.1.1.1.1.5 |
Kepala Tukang |
0.078 |
OH |
236.200,00 |
18.423,60 |
123.1.1.1.1.6 |
Mandor |
0.013 |
OH |
206.800,00 |
2.688,40 |
123.1.1.1.1.14 |
Pekerja Terlatih |
3.12 |
OH |
150.800,00 |
470.495,98 |
123.1.1.1.1.23 |
Tukang |
1.56 |
OH |
177.500,00 |
276.899,99 |
|
|
|
|
Jumlah |
768.507,97 |
|
Bahan/Material: |
|
|
|
|
117.1.1.1.22.346 |
Kusen Aluminium Tipe J 1 K |
1 |
unit |
2.766.800,00 |
2.766.800,00 |
|
|
|
|
Jumlah |
2.766.800,00 |
|
Sewa Peralatan: |
|
|
|
|
|
|
|
|
Jumlah |
0,00 |
|
|
|
|
Nilai HSPK |
3.535.307,97 |
| 2020 | 24.1.10.85 | Pemasangan Kusen Aluminium Type J 1 K | unit | 3.535.307,97 | Tidak Dipakai | |
1418 |
NOMOR |
URAIAN KEGIATAN |
KOEF. |
SAT |
HARGA SATUAN |
HARGA |
24.1.10.86 |
Pemasangan Kusen Aluminium Type J 2 |
|
unit |
|
|
|
Upah: |
|
|
|
|
123.1.1.1.1.5 |
Kepala Tukang |
0.084 |
OH |
236.200,00 |
19.840,80 |
123.1.1.1.1.6 |
Mandor |
0.014 |
OH |
206.800,00 |
2.895,20 |
123.1.1.1.1.14 |
Pekerja Terlatih |
3.36 |
OH |
150.800,00 |
506.687,98 |
123.1.1.1.1.23 |
Tukang |
1.68 |
OH |
177.500,00 |
298.199,99 |
|
|
|
|
Jumlah |
827.623,97 |
|
Bahan/Material: |
|
|
|
|
117.1.1.1.22.347 |
Kusen Aluminium Tipe J 2 |
1 |
unit |
2.809.500,00 |
2.809.500,00 |
|
|
|
|
Jumlah |
2.809.500,00 |
|
Sewa Peralatan: |
|
|
|
|
|
|
|
|
Jumlah |
0,00 |
|
|
|
|
Nilai HSPK |
3.637.123,97 |
| 2020 | 24.1.10.86 | Pemasangan Kusen Aluminium Type J 2 | unit | 3.637.123,97 | Tidak Dipakai | |
1419 |
NOMOR |
URAIAN KEGIATAN |
KOEF. |
SAT |
HARGA SATUAN |
HARGA |
24.1.10.87 |
Pemasangan Kusen Aluminium Type J 2 K |
|
unit |
|
|
|
Upah: |
|
|
|
|
123.1.1.1.1.5 |
Kepala Tukang |
0.054 |
OH |
236.200,00 |
12.754,80 |
123.1.1.1.1.6 |
Mandor |
0.009 |
OH |
206.800,00 |
1.861,20 |
123.1.1.1.1.14 |
Pekerja Terlatih |
2.16 |
OH |
150.800,00 |
325.728,01 |
123.1.1.1.1.23 |
Tukang |
1.08 |
OH |
177.500,00 |
191.700,01 |
|
|
|
|
Jumlah |
532.044,02 |
|
Bahan/Material: |
|
|
|
|
117.1.1.1.22.348 |
Kusen Aluminium Tipe J 2 K |
1 |
unit |
1.994.400,00 |
1.994.400,00 |
|
|
|
|
Jumlah |
1.994.400,00 |
|
Sewa Peralatan: |
|
|
|
|
|
|
|
|
Jumlah |
0,00 |
|
|
|
|
Nilai HSPK |
2.526.444,02 |
| 2020 | 24.1.10.87 | Pemasangan Kusen Aluminium Type J 2 K | unit | 2.526.444,02 | Tidak Dipakai | |
1420 |
NOMOR |
URAIAN KEGIATAN |
KOEF. |
SAT |
HARGA SATUAN |
HARGA |
24.1.10.88 |
Pemasangan Kusen Aluminium Type J 3 |
|
unit |
|
|
|
Upah: |
|
|
|
|
123.1.1.1.1.5 |
Kepala Tukang |
0.06 |
OH |
236.200,00 |
14.172,00 |
123.1.1.1.1.6 |
Mandor |
0.01 |
OH |
206.800,00 |
2.068,00 |
123.1.1.1.1.14 |
Pekerja Terlatih |
2.4 |
OH |
150.800,00 |
361.920,01 |
123.1.1.1.1.23 |
Tukang |
1.2 |
OH |
177.500,00 |
213.000,01 |
|
|
|
|
Jumlah |
591.160,02 |
|
Bahan/Material: |
|
|
|
|
117.1.1.1.22.349 |
Kusen Aluminium Tipe J 3 |
1 |
unit |
2.273.200,00 |
2.273.200,00 |
|
|
|
|
Jumlah |
2.273.200,00 |
|
Sewa Peralatan: |
|
|
|
|
|
|
|
|
Jumlah |
0,00 |
|
|
|
|
Nilai HSPK |
2.864.360,02 |
| 2020 | 24.1.10.88 | Pemasangan Kusen Aluminium Type J 3 | unit | 2.864.360,02 | Tidak Dipakai | |